water,  combustion  gas,  etc.  flowing  in  the  heat  exchanger  tubes  and  a  part  of  water  in  it  is 
evaporated  to  result  in  increasing  its  concentration  to  the  original  condition.  The  concentrated 
solution  flows  into  the  absorber  and  absorbs  the  refrigerant  vapor  again.  While,  the  evaporated 
refrigerant vapor flows into the condenser and is cooled down by cooling water running in the heat 
exchanger  tubes  to  be  condensed  and  liquefied.  The  condensed  water  is  supplied  to  the 
evaporator as refrigerant. 

 
 
   
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
            As mentioned above, the absorption chiller consisting of the evaporator, absorber, generator and 

condenser produces chilled water by latent heat in the process of such change in phase as water 
- vapor 

– water for water and concentrated solution – diluted solution – concentrated solution for 

lithium  bromide  solution,  while  absorbing  the  vapor  by  the  lithium  bromide  solution  in  the  high 
vacuum system repeatedly and continuously. 

   
 
 
 
 
 
 
 
 
   
 

 
 
 
 
 
 
 
 
 
 
 
 
 
 

Condensed water 

Содержание HDFN-80-1400

Страница 1: ...HYUNDAI CLIMATE CONTORL CO LTD Operation Instructions Gas Oil Direct fired Absorption Chiller heater Models HDFN 80 1400...

Страница 2: ...dling and maintenance service of the absorption chiller heater however its excellent performance and durability would not come to play This manual gives information on the construction functions of th...

Страница 3: ...sufficiently If the air required for combustion is in short it may cause an oxygen poor accident 8 Do NOT put heavy materials on the absorption chiller heater and the control panel It may cause injury...

Страница 4: ...is completed as per the operation sequence to eliminate a possibility of tube damages etc NEVER stop the operation of the cooling water pump as well until it is completed as per the operating sequenc...

Страница 5: ...ock a fire or a burn 8 Be sure to use the fuses with correct capacity Without using them it may cause a machine trouble or a fire 9 Do NOT let the absorption chiller heater and the control panel get w...

Страница 6: ...ure Control 17 3 3 Solution Flow Rate Control 18 3 4 Low Load Control 19 3 5 Emergency Stop 19 3 6 Protective Devices 19 CHAPTER 2 PREPARATION AND OPERATION 4 Preparation for Operation 24 4 1 Evacuati...

Страница 7: ...6 9 1 3 Recording operation data 46 9 1 4 Others 46 9 2 Periodical Inspection 46 9 3 Maintenance of Purge Pump 47 9 4 Cooling Water Control 50 9 4 1 Temperature control 50 9 4 2 Water quality control...

Страница 8: ...ium Bromide Solution 64 2 1 General Properties 64 2 2 Solubility 65 2 3 Specific Gravity 65 2 4 Specific Heat 65 2 5 Vapor Pressure 65 2 6 PH 65 2 7 Corrosiveness 65 2 8 Others 65 3 Adjustment Procedu...

Страница 9: ...solution dilute lithium bromide solution hereinafter referred to dilute solution being collected at the bottom of the shell The absorption heat generated here is removed outside by the cooling water f...

Страница 10: ...ructure to keep high vacuum However hydrogen gas generates when the anti corrosion thin film is formed in the vessel The purge system is provided to collect the hydrogen gas and non condensable gas su...

Страница 11: ...11 Fig 1 1 External View of Chiller heater...

Страница 12: ...ce valve V 25 Service valve V 28 By pass valve for de crystallization V 35 By pass valve for de crystallization V 41 Valve for purging changeover V 42 Sight glass Sight glass Sight glass Valve for pur...

Страница 13: ...pass valve for de crystallization V 41 Sight glass Sight glass Sight glass Valve for purging V 2 Valve for purging V 3 Valve for purging V 4 Purge pump Manometer Chilled hot water inlet Chilled hot wa...

Страница 14: ...he upper shell containing the condenser and low pressure generator is kept at a high vacuum of about 60 mmHg abs the condensed refrigerant is sent to the evaporator by differential pressure between th...

Страница 15: ...is sprayed on the surface of the absorber tubes to be cooled down in the low temperature heat exchanger Point i a A state where the concentrated solution absorbs the refrigerant to be diluted in the a...

Страница 16: ...16...

Страница 17: ...Compare to the set point Valve action Fuel control Rise up Open Chilled water Balanced Stop outlet temperature Go down Close 3 2 Hot Water Temperature Control The signal sent from the temperature sen...

Страница 18: ...olution level with the electrode the speed of solution pump is controlled to keep the correct level Level too high Solution pump stop Level high Speed of solution pump decrease Solution level in high...

Страница 19: ...on due to external cause the main gas valve closes automatically to stop operation of the chiller heater Refer to the Table 3 1 List of Protective Devices for detail stop of operation 3 6 Protective D...

Страница 20: ...20 Fig 3 5 Operation Flow Chart...

Страница 21: ...21...

Страница 22: ...be open when air pressure falls Do Do Applied for gas fired and oil fired with proportional control type Flame detector UV Detect misfire and reduced fire Do Do Pressure switch for high pressure gener...

Страница 23: ...Over current relay for refrigerant pump motor M2 49 Rating current Do Combustion shut down and sol Pump stop Refrigeration pump motor protection Over current relay for purge motor M3 49 Rating curren...

Страница 24: ...on 2 Connect the solution service valve with the vessel with a vacuum vinyl hose and fill the hose with solution to purge out air 3 Insert the end of the vinyl hose into the bottom of the vessel and f...

Страница 25: ...a vacuum vessel separately and connect it with the service valve for discharge And then open the service valve for discharge to discharge refrigerant after checking if the vessel is vacuumed If soluti...

Страница 26: ...ary wiring between the motor and control panel phase checking test is done at the factory But for safety purpose confirm the motor rotating direction by checking its discharge pressure current operati...

Страница 27: ...may not be stabilized and evaporation temperature is likely to change abruptly which may cause freezing or other troubles However in case load is stabilized at factory etc there is no need for such t...

Страница 28: ...he level of 1 2 to 1 3 from the bottom of the sight glass of the absorber And then check the concentration of the concentrated solution with the solution temperature at the outlet of the generator the...

Страница 29: ...29 5 3 Adjustment Procedure for Trial Operation 5 3 1 Outline of solution flow The outline of the solution flow and the position of the valves are shown as below Fig 5 2 Outline Location of Valves...

Страница 30: ...e control valve manual butterfly valve Location Intermediate concentration solution line From the high temp heat exchanger outlet to the low pressure generator inlet 30 Function Flow rate control of i...

Страница 31: ...nd heating Diaphragm valve Location By pass line from the dilute solution pump discharge to the refrigerant pump discharge Fully opened Be sure not to open the valve excessively Excessive opening may...

Страница 32: ...procedure 1 Adjust the flow rate of GL by the valve V 31 2 Adjust the flow rate of GL 1 by the valve V 30 GL2 changes because GL GL1 GL2 Be sure that the total flow rate GL changes slightly due to pr...

Страница 33: ...pressure generator 160 165 140 145 Adjustment procedure of pressure and solution temperature at the high pressure generator Pressure at the High Pressure Generator Solution Temperature at High Pressur...

Страница 34: ...0 10 0 10 7 8 5 9 3 450 20 8 22 5 11 3 12 1 9 5 10 4 500 23 2 25 0 12 5 13 4 10 7 11 6 600 22 8 24 2 12 2 13 0 10 6 11 3 1 5 2 5 700 26 5 28 2 14 2 15 1 12 3 13 1 800 30 2 32 2 16 2 17 2 14 1 14 9 90...

Страница 35: ...35...

Страница 36: ...ss button switch START When switched to START the chiller heater is operated automatically as per the following process 1 The solution pump starts 2 The forced fan starts and pre purges for about 90 s...

Страница 37: ...and refrigerant pump runs continuously 3 When the solution temperature of the high pressure generator drops below 110 the refrigerant pump stops 4 After about 20 minutes of stopping operation the sol...

Страница 38: ...d temp of H P gen Refrigerant pump operation Igniting system Stop Temperature control start Main stop switch ON Dilute operation Approx 20 min Damper low Combustion position Solution pump stop Below p...

Страница 39: ...0 for the stoppage order of heating operation Fig 5 10 Cooling Operation Flow Diagram STOP Start switch ON Hot water thermostat ON with heating load N Hot water flow rate o H P gen Solution level r H...

Страница 40: ...nerator is low at starting The service operation pump up the solution to the high pressure generator to provide the condition suitable for start up 2 In the case that crystallization of solution occur...

Страница 41: ...confirm that the number of non condensable gas bubbles is less than 2 per minute The degree of vacuum must be below 2 mmHg Note The ballast valve must be kept open during vacuuming the chiller heater...

Страница 42: ...hiller heater is operating 2 In heating season be sure to perform the purging while the chiller heater stops 3 In heating season be sure to close the service valves for maintenance and for manometer 4...

Страница 43: ...condensable gas only is accumulated in the reservoir 3 The non condensable gas in the reservoir is purged into the atmosphere by simultaneous use of the purge pump 4 Operation frequency of purge pump...

Страница 44: ...e chiller heater has corrosivity an inhibitor is added to the solution When anti corrosive thin film is formed on the inside surface of the chiller heater by the inhibitor hydrogen gas generates The a...

Страница 45: ...by pass valve and damp the refrigerant to the absorber When the refrigerant level is out of sight from the evaporator sight glass close the by pass valve 3 Carry out service level is out of sight from...

Страница 46: ...the discharge pipe of the vacuum pump and soak the other end of the vinyl hose into the pump oil container Be sure that the point of the hose is not soaked in the oil more than 6 mm ii Close the manua...

Страница 47: ...stallation condition operating hour and so forth However it is inevitable It is essential in order to maintain the chiller heater in normal and good condition to know the state of the chiller heater c...

Страница 48: ...rature 4 Combustion Condition Visual Chilled Water 5 Inlet Temperature 6 Outlet Temperature 7 Flow Rate h Hot Water 8 Inlet Temperature 9 Outlet Temperature 10 Flow Rate h Cooling Water 11 Inlet Tempe...

Страница 49: ...ed Fan Check Forced Fan Overhaul Burner Nozzle Overhaul Explosion Door Check Refrigerant Check Solution Sampling Thermometer Check Pressure Gauge Check Chilled Hot Water Pump Cooling Water Pump Coolin...

Страница 50: ...e efficiency due to deposit of scales on the heat exchangers and may also cause a serious accident such as submersion of the chiller heater by the corrosion damage of heat transfer tubes perform water...

Страница 51: ...ut down period periodical circulation of the cooling water by the pump is recommended This is for equalization of the density of chemicals in the cooling water In case of leaving the cooling water lin...

Страница 52: ...rs do not remain inside the tubes and water boxes 3 Check if the packing of the sluice plate and flange are not damaged and fitted correctly 4 Check if the sluice plate is set in correctly between the...

Страница 53: ...fter preparing at a prescribed concentration in a container charge the chemical from the drain port and make it circulate by circulation pump The circulation time depends on the amount of removal of t...

Страница 54: ...first Generally air volume required for combustion theoretical air volume is 1m3 1 000 kcal regardless of kind of fuel The biggest problem for the burner is combustion under insufficient air The cont...

Страница 55: ...pilot and main governors for actuation and controllability Strainer Clog Pay attention to gas pressure or oil pressure during operation and clean it when it goes down Forced Fan Driving parts and bear...

Страница 56: ...tor Clean the glass of the flame detector Gas pressure switch High and low applied for gas fired type Check the deviation between actuation and setting point by changing gas pressure or setting point...

Страница 57: ...rate is short Check the cooling Check cooling water temperature control system Tubes for cooling water are dirty Check the cooling water pump and cooling water system Clean the cooling water tubes Not...

Страница 58: ...r Temperature low switch U6 Chilled water load is too small Chilled water temperature is too low Check the setting point of chilled water thermostat and chilled water controller Check the chilled wate...

Страница 59: ...ut taking no countermeasures crystallization may take place because of no dilution operation In case of power failure open the damp valve located at the lower part of the low pressure generator to dra...

Страница 60: ...DIX Technical Information and Data for Reference 1 Principle of Absorption Chiller heater 2 Properties of Lithium Bromide Solution 3 Adjustment Procedure of Inhibitor for Lithium Bromide Solution 4 Sp...

Страница 61: ...ressure kg ata Saturation temperature Over atmosphere Atmosphere Vacuum 20 10 8 5 1 0 21 11 9 6 2 760 mmHg 634 0 355 2 149 4 92 5 55 3 17 5 9 2 7 5 6 5 6 1 5 7 213 86 183 20 174 53 158 09 119 61 100 0...

Страница 62: ...ter by vacuum pump but such a way is not good because the volume becomes so big In the absorption chiller the refrigerant vapor is absorbed into lithium bromide solution As the vapor s partial pressur...

Страница 63: ...unning in the heat exchanger tubes to be condensed and liquefied The condensed water is supplied to the evaporator as refrigerant As mentioned above the absorption chiller consisting of the evaporator...

Страница 64: ...Bromide Solution 2 1 General Properties As supposed from the fact that lithium and bromide belong to alkali and halogen group the general chemical property of lithium bromide is similar to salt and it...

Страница 65: ...gh efficiency is expected in the absorption chiller heater using water and lithium bromide 2 5 Vapor Pressure The essential reason why lithium bromide is used as absorbent in the chiller heater is tha...

Страница 66: ...66 Fig 8 Lithium Bromide Temperature Specific Gravity Concentration Curve...

Страница 67: ...67...

Страница 68: ...on of the chiller heater for 5 days or more Besides it must be sampled after continuous operation of the chiller heater for 5 hours or more on the sampling day 2 At dilution operation discharge refrig...

Страница 69: ...y metals Especially be careful not to put LiOH in the eyes 4 Spill over As the cooling load changes both the refrigerant level of the evaporator and the solution level of the absorber also change Fig...