Recommended Material List
The following is a list of standard and recommended materials that are used for a StoreConnect installa-
tion. The StoreConnect Equipment and any quantities will be specific to the actual estimate, proposal and
job site. The electrician and carpenter material lists are general requirements. It is recommended that a
site visit take place prior to installation day in order to properly plan the layout and any carpentry, electri-
cal conduit, and additional electrical connections that may be required.
StoreConnect General Installation Guidelines
Time Allotment
A typical StoreConnect Lite installation generally takes 2 team members (1 being an electrician)
½ - 1 day to properly install the solution. StoreConnect installation with power meters can take anywhere
from ½ to 2 days to complete. For a distributed protocol application, the duration may be longer due to
the location of the assets and connection points at the site. In this case, we would recommend 1-4 days
for an installation. Be aware of where the network switch for the store is located. It may be required that
the installation have a Cat5/6 cable run from the SC-21 to the network switch which will also include
additional time.
Space Constraints & Planning
Depending on the refrigeration system equipment configuration, space may be an issue. If the site in-
cludes Power Meters, it is best to locate the Power Meters on the rack or protocols in order to minimize
any extension of the connected Current Transformers. The SC-21 can be mounted to any wall, preferably
close to the site network main switch in the refrigeration system room. Note: The SC-21 must be mount-
ed with the SMA Antenna connectors facing up.
Internet Connectivity
Internet connections can made in 2 ways: 1) via the internal LTE Modem, 2) through the stores LAN
(local area network) or stores VLAN (vendor network) using the WAN Ethernet port on the SC-21. If the
site will be using the LAN connection, a separate site networking document and release will need to be
completed prior to installation in order to verify and test network requirements.
Ethernet Cables
Cat5e or Cat6 shielded cable must be used along
with shielded RJ45 connectors to reduce unintended
radio emissions. The RJ45’s look like the following: