StoreConnect Site Installation
In the Pre-Installation Form, the electricians can visualize how a site is supposed to be installed given the
site’s specific equipment demands. A typical installation takes at least a full day of work and can take even
longer if the store is a protocol site. The site installation will also require the electrician and site personnel
to complete some forms of provisioning while on site. The list below is the step-by-step procedure neces-
sary to successfully complete a StoreConnect installation.
Find a location for StoreConnect hardware
If the site is using Cellular LTE for it’s internet connection, it is important to find a location for the SC-21
that has good cellular reception and an AC power outlet nearby. Finding a central location between the
refrigeration controllers and the power meters to minimize Cat5 cabling runs will reduce install time.
Generally, a good location for the SC-21 is in the site’s networking closet or inside the mechanical room
near the refrigeration racks. Power meter locations are best placed in close proximity to their respective
suction group, rack or protocol unit.
Install the SC-21
•
Electrical Connection:
Requires a 120V connection, via the included power supply adapter.
Requirements: Standard AC wall outlet nearby, reasonable cell reception.
• Hang SC-21:
Typically, the SC-21 (the HUB) is located on a wall across from the refrigeration systems
equipment. Mount the SC-21 in the designated location.
Install or find a 120V plug for the power supply to the SC-21.
Connect antennas to the SMA antenna connectors on the top of the unit.
Using the adhesive on the antennas, stick the antennas to a non-metallic surface.
Plug SC-21 AC power adapter into a power outlet.
•
Intermediate Testing:
Be sure the power source is supplying power to the SC-21. You can verify this visually by making
sure there is a green heartbeat LED on the SC-21.