4)

 

Hoist Assembled Posts and Headers into Anchors 

Prepare four scrap 2x4 to temporarily brace the posts after being hoisted into place. 
Hoist one post and header structure upright and place bottom end of posts into anchors. Use a 
level to ensure that posts are plumb and secure into anchors with choice of hardware. Consult 
Simpson installation instructions for proper procedure. Brace the posts laterally using 2x4 to 
keep them from falling over during assembly. Secure the 2x4 braces to both the post and the 
ground. 

 

Repeat for opposite side. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Содержание Napa

Страница 1: ...Napa Pergola Assembly Instructions Napa Pergola Assembly Instructions ...

Страница 2: ...easuring Tape Pencil 8 4ft Long Scrap 2x4 for use as temporary bracing 1 Layout Post Anchors On Level ground mark location of the 4x included post anchors Ensure that diagonal measurements are equal to maintain square dimensions 2 Secure Post Anchors Install Post anchors in marked location Consult Simpson installation instructions for proper procedure ...

Страница 3: ...pre drilled holes of 3x10 Header 2 upon post Ensure equal 92 spacing along the length of the posts and use a framing square and bubble level to maintain square dimensions Mark hole location and drill holes through posts using 7 8 drill bit Assemble two 3x10 Headers on both sides of post using provided hardware Repeat for remaining two posts and 3x10 headers ...

Страница 4: ...re upright and place bottom end of posts into anchors Use a level to ensure that posts are plumb and secure into anchors with choice of hardware Consult Simpson installation instructions for proper procedure Brace the posts laterally using 2x4 to keep them from falling over during assembly Secure the 2x4 braces to both the post and the ground Repeat for opposite side ...

Страница 5: ...ss top of 3x10 Headers 2 Center pre drilled holes upon post and mark location Drill holes through posts using 7 8 drill bit Assemble two 3x8 Headers on both sides of post using provided hardware Repeat for remaining two 3x8 headers on opposite side ...

Страница 6: ...ide edge of 3x6 Header 4 Hang over the edge 7 on each side to center the header Place remaining five 3x6 Headers along length with 14 spacing between each Secure 3x6 Headers to 3x8 Headers with woodscrews or nails Pre drilling pilot holes is recommended to prevent splitting ...

Страница 7: ...e of 2x2 Lath 5 Hang over the edge 9 on each side to center the lath Place remaining twenty six pieces of 2x2 Lath along length with 2 spacing between each Secure 2x2 Lath to 3x6 Headers with woodscrews or nails Pre drilling pilot holes is recommended to prevent splitting ...