Nitrogen injection volume range: 6–12 L/min. The nitrogen injection time for the entire
system is greater than 2 minutes. The nitrogen injection time after pipe welding is greater than
1 minute.
Slowly charge nitrogen into pipes through the discharge pipe needle valve when welding
gas pipes.
Slowly charge nitrogen into pipes through the liquid pipe needle valve when welding
liquid pipes.
Figure 3-33
Routing pipes from the bottom
(1) Gas pipe
(2) Liquid pipe
Figure 3-34
Welding schematic diagram
Step 2
Take out two straight pipes whose diameters are 3/4 inch and 5/8 inch respectively from the
fitting bag, and weld the two pipes, as shown in