FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
4 Hardware Installation Preparations
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
24
Figure 4-4
Assembling a base
1.
Adjust the base depth based on the cabinet depth.
2.
Tighten the six M8x20 bolt assemblies on the telescopic rod using a Phillips screwdriver,
as shown by (1) in
3.
Assemble the telescopic rod and base using eight M8x20 bolt assemblies, and then
tighten all bolt assemblies using a Phillips screwdriver, as shown by (2) in
4.
Tighten all height locking bolts using a torque wrench, as shown by (3) in
----End
4.1.1.3.2 Positioning Bases
Procedure
Step 1
Determine the correct installation position for the smart module based on the onsite
engineering layout diagram.
Step 2
Use a laser locator to mark two lines that are perpendicular to each other in a corner of the
planned installation position.
If no laser locator is available, use a right angle and thin rope for marking the two perpendicular lines.
Step 3
Use a marker to mark the outline of the cabinet on the floor and place one corner of the
outline at the crossing point of the perpendicular lines.