5.2
Filling the heating system
Filling of the heating system must be carried out by trained
personnel. The fill and make-up water must comply with
the quality requirements in the relevant state or country
(see chapter 5.1).
5.3
Filling the water heater (if fitted)
The heating boiler may be put into operation even when
the water heater is not filled.
5.4
Commissioning
Important:
On first commissioning, check that all safety and
control devices are functioning properly.
Operation and maintenance of the system must be
explained in detail to the operator.
Before commissioning, the neutralisation box
(where fitted) must be filled with water.
5.5
Oil burner
Setting the burner must also be carried out by a specialist
and the setting must correspond to the heat demand of
the system.
Please see the technical information / assembly instruc-
tions supplied with the burner.
Burners are fitted with oil preheating and
when restarted are ready for operation again
after about 2 minutes’ delay.
5.6
Handover to the operator/storage
Have the operator confirm in writing that the methods of
operating and service procedures have been explained
and that he has received a copy of the relevant operating
instructions (see sample 50). The system manufacturer
is responsible for providing operating instructions for the
whole plant. The technical information / installation in-
structions must be kept with the plant at all times.