CR7075 TWO-STAGE LIGHTING CONTROLLER
7
63-2180—1
CHECKOUT
In the following procedures, refer to the diagram inside the
CR7075A cover or Fig. 3. These show locations of all
operating controls, LED lights, and wiring connection points.
Initial Adjustments
1.
Adjust both light level potentiometers to the fully
clockwise position (#1 index level).
2.
Place the SET-RUN switch to the RUN position.
Calibration
After the controller and photocell sensor are installed (with
wiring and settings verified), and the photocell has been
exposed to light for 16 hours, apply power. The light intensity
threshold levels can be calibrated when the desired outdoor
light level has occurred.
NOTES:
—
Calibration achieves best results when making
adjustments at or near the light conditions
required for switching the equipment.
—
Attempting calibration at extreme light conditions
can cause switching to be unachievable.
1.
At the desired outdoor light level place SET-RUN switch
to the SET position.
2.
Slowly rotate stage 1 light level potentiometer counter-
clockwise until the stage 1 LED lights.
3.
Stage 1 is now calibrated to the light level existing at the
sensor and the stage 1 load is energized.
4.
Return the SET-RUN switch to the RUN position.
NOTE: To calibrate stage 2, repeat this process
except adjust the stage 2 light level
potentiometer.
IMPORTANT
After initial setup is complete, make certain the
switch is in the RUN position to avoid short cycling
the loads.
NOTE: The SET-RUN switch removes the integrating time
delay (short-cycle protection) circuitry in the SET
position. In the RUN position (normal operation) the
calibrated light level must be present for 30 seconds
before the load switches.