35
9.1
Fill Boiler With Water And Purge Air
NOTICE
To maintain boiler efficiency and prevent boiling
inside the heat exchanger, flush entire heating
system until clean.
•
Flush heating system, including all heating zones.
•
Fill boiler with potable water.
•
Fill boiler and system piping with water (or
antifreeze-water solution, if used). See antifreeze
information page 13. Purge air from boiler using
safety relief valve. Purge air from system piping.
•
Inspect system piping and boiler connections. Repair
any leaks immediately.
•
Activate all heating zones and calls for heat,
including CH calls and DHW calls (if available).
•
Close manual gas shut off valve. Let system run for
30 minutes. When boiler goes into lockout, reset
boiler by pressing "Reset" button until boiler resets.
•
Do not open gas shutoff valve until all air is purged
from system.
9.2
Fill Condensate Trap with Water
•
Remove spring tension clip from clear hose attached
to barbed fitting at bottom of boiler chassis.
See
figure 9-1.
•
Disconnect hose from barbed fitting.
•
Remove barbed fitting from boiler.
•
Attach supplied condensate trap to barbed fitting
using pipe tape.
•
Fill trap through fitting with approximately 2 cup
(473 ml) water.
•
Place barbed fitting back through bottom of chassis.
•
Reassemble clear tube to barbed fitting.
•
Secure tube to barbed fittting with spring tension clip.
See figure 9-1.
FIGURE 9-1 Condensate Drain Assembly
NOTICE
IMPORTANT: Condensate trap must be manually
filled with water at initial start up.
9 - START UP PROCEDURE
Condensate
Collector
Remove Spring
Tension Clip
Remove Hose
Barb
Attach Supplied
Condensate Trap
to Hose Barb
Secure Hose onto
Hose Barb with
Spring Tension
Clip
Содержание VX-050
Страница 49: ...49 13 TROUBLE SHOOTING...
Страница 51: ...51 13 TROUBLE SHOOTING...
Страница 63: ...63 14 1 Connection Diagram 050 075 100 MBH 14 WIRING DIAGRAM...
Страница 64: ...64 14 2 Schematic Diagram of Ladder Form 050 075 100 MBH 14 WIRING DIAGRAM...
Страница 65: ...65 14 3 Connection Diagram 150 200 MBH 14 WIRING DIAGRAM...
Страница 66: ...66 14 4 Schematic Diagram of Ladder Form 150 200 MBH 14 WIRING DIAGRAM...
Страница 83: ...83 PRIMARY LOOP EQUIVALENT LENGTH CALCULATION PUMP SELECTION 50 75 100 MBH...
Страница 84: ...84 PRIMARY LOOP EQUIVALENT LENGTH CALCULATION PUMP SELECTION 50 75 100 MBH...
Страница 85: ...85 PRIMARY LOOP EQUIVALENT LENGTH CALCULATION PUMP SELECTION 150 200 MBH...
Страница 86: ...86 PRIMARY LOOP EQUIVALENT LENGTH CALCULATION PUMP SELECTION 150 200 MBH...
Страница 87: ...87 NOTES...
Страница 88: ...DUNKIRK BOILERS 2201 Dwyer Avenue Utica NY 13501 web site www ecrinternational com...