Soffit element installation package –
KWL 45-160 LE-RP
Installation and Operating Instructions
4
4 .0 Positioning
The following minimum clearances to the window aperture must be taken into account for positioning the soffit channel
or the core hole drilling (see Fig. 3):
– Horizontal clearance from core hole to soffit (finished plaster): min. 220 mm to max. 500 mm
– Vertical clearance from core hole to window lintel: min. 300 mm
CHAPTER 4
INSTALLATION
Kernbohrung
≥ ø 162 mit Gefälle nach außen ≥ ø 172 horizontal
220 - 500
min. 300
Leerrohr für
Anschlussleitung
Überdämmung
Fensterrahmen
+ Fertigputz
Putzrahmen
Fenstersturz
Laibungskanal
Wandinnenseite
Fig .3
All dimensions in mm
EN
Soffit channel
Window lintel
Internal side of wall
Plaster frame
Over-insulation
window frame
+ finished
plaster
Empty conduit for
connection cable
Core hole
with gradient to outside
horizontal
Содержание KWL 45-160 LE-RP
Страница 11: ...Rohbaupaket Laibungselement KWL 45 160 LE RP Montage und Betriebsvorschrift 10 DE ...
Страница 21: ...Soffit element installation package KWL 45 160 LE RP Installation and Operating Instructions 10 EN ...
Страница 31: ...Kit gros oeuvre en tableau de fenêtre KWL 45 160 LE RP Notice de montage et d utilisation 10 FR ...