HELIOS COMBO SPH3600/5000-BL
5 Operation Instruction
33
5
Operation Instruction
This chapter introduces inverter startup, shutdown and monitoring setting.
5.1 Opearaion Announcements
⚫
Load requirements in the BACK UP port is as below:
−
Resistive load
≤
2.5kw;
−
Capacitive load
≤
1.5kvar;
−
Inductive load
≤
1.5kvar.
⚫
There may exists suspended voltage between live wire and neutral wire with grounding wire in
the BACKUP port and GRID port. Don't touch live wire and neutral wire directly.
⚫
If there has overload protection or short circuit protection, power down inverter and then power it
on again.
5.2 Turn on Inverter
Step 1
Switch on AC output switch.
Step 2
Switch on DC input switch.
Step 3
Switch on battery switch.
----End
5.3 Turn off Inverter
Step 1
Switch off all switches.
Step 2
Wait all indicators are off.
----End
5.4 Monitoring Setting
If it needs to perform monitoring setting, connect PC with inverter and download WiseEnergy in the
official website.