Heat & Glo • SOHO-N-AU • 2197-900 Rev. C • 9/09
16
Installing the Ceiling Firestop
• Frame an opening 254 mm by 254 mm
whenever the system penetrates a ceiling/
fl oor (see Figure 6.3). A steeply slanted
roof may require an enlarged opening
size in order to maintain proper fl ue pipe
clearances.
• Frame the area with the same sized
lumber as used in ceiling/fl oor joist.
• When installing a top fl ue vertical ter-
mination appliance the hole should be
directly above the appliance, unless the
fl ue is offset.
• Do not pack insulation around the fl ue.
Insulation must be kept away from the
pipe.
Installing Attic Shield
Note:
An additional ceiling fi restop is not
required if attic shield is used.
• Frame opening for attic shield.
• Attic shield may be installed above or
below ceiling (see Figure 6.4).
• Secure with three fasteners on each
side.
• Fold tabs at top of attic shield in toward
fl ue pipe. Tabs must keep fl ue pipe cen-
tered within shield.
• Field construct additional shield height if
insulation is deeper than height of attic
shield.
C. Vertical Penetration Framing
Figure 6.3
ATTIC
ABOVE
A
B
Figure 6.4 Installing the Attic Shield
A
B
SL PIPE
254 mm 254
mm
3 FASTENERS
PER SIDE
BEND TABS IN
AROUND PIPE
ATTIC SHIELD INSTALLED
ABOVE CEILING
ATTIC SHIELD INSTALLED
BELOW CEILING
Fire Hazard
Keep loose materials or blown
insulation from touching the
fl ue pipe.
• Hearth & Home Technologies requires
the use of an attic shield.