9. INSTALLING THE HEALY VP1000 SYSTEM
NOTICE: WHEN DRILLING HOLES, ASSURE THAT THERE ARE NO HAZARDOUS
VAPORS PRESENT AND DO NOT ALLOW CHIPS TO FALL DOWN INTO THE
HYDRAULICS
AREA.
In order to get the vapor tubing from the pump into the vapor plumbing area, it is
necessary to drill or punch two 1-1/8” holes on the sheet metal column near the edge
of the shelf, see photo E. Use a tape measure and mark the centerline of the holes to
be 1-1/4” in from the front edge of the sheet metal column. Measure down from the
top of the column 5-1/2” and mark on the 1-1/4” centerline, measure down an
additional 6-3/4” and mark on the centerline. These marks are the centers of the holes
for the vapor pipes going to the VP1000. DO NOT DRILL – verify positions in the next
steps.
Get the vapor pump and install a 1/2” NPT x 5/8” flare elbow fitting into the ‘IN’ and
‘OUT’ ports using tape, not pipe dope. Looking at the face of the pump, completely
tighten both fittings so they are facing the right.
Position the pump on top of the sheet metal shelf over the electrical junction box on
top of the electronics cabinet, with the fittings pointing toward the hydraulics cabinet
and overhanging the edge of the shelf about 1/4”.
Slide the pump to fit against the hydraulics cabinet and position so as to allow for
matching the location of holes that need to be drilled through the sheet metal.
Satisfied that the fittings and hole marks line up, remove the pump and drill the two,
1-1/8”
holes,
marked
above.
Position the pump assembly on top of the sheet metal shelf and slide over so that the
ports are accessible from the hydraulics area.
10. CONNECTING VAPOR LINES: (See Photos K, L, M & N)
NOTICE:
ALL VAPOR LINES MUST BE INSTALLED TO BE NATURALLY DRAINING,
WITHOUT ANY DIPS OR TRAPS THAT WOULD CAUSE BLOCKAGE.