5 Commissioning the system – Procedure
45
1.
Open the ash door (1).
2.
Open the upright grate flap (2).
3.
Take the flat grate elements (3) out toward the front.
4.
Set the grate lifting bar (4) on the support.
5.
Insert the flat grate elements (3).
6.
Close the boiler in the reverse order.
✓
The grate lifting bar is now set.
Figure 5/3 - Grate lifter
1
2
4
3
The three flat grate elements are of differing width. Make sure that
the flat grate elements are put back in the correct manner and
order.
Caution!
Danger of injury
The flat grate elements are heavy. Hands and fingers could be
crushed during their removal/installation.
Exercise caution so that your hands and fingers do not become
caught.