background image

 

HAMWORTHY HEATING LTD 

 

14 

FLEET V series 

 

500001213/G 

 

 

5.0 BOILER ASSEMBLY 

 

5.1 General  

 

Boilers are despatched to site as fully assembled units. The flue manifold and  pipe work set (where applicable) 
are the only items that will need assembling on site. 

 

Should access be an issue, the boiler modules can be dismantled to assist delivery into the plant room. To carry 
out this process, carefully remove the top panel, the front cover and side panels from each module. This will give 
access to 4 M10 nuts per module, securing the upper module to the lower module or base frame. Great care 

MUST

 be taken in separating and re-assembling the modules when in the required location, recognising the 

weight - refer to section 2. It is recommended that M10 lifting eyes are fitted to the boiler chassis in the four 
locations provided in the upright frame. 
During assembly it is important to take care to prevent damage to the boiler casing. 

 

Boiler positioning must allow the minimum clearances detailed in Section 3.0 to facilitate access for flue and pipe 
work connections as well as maintenance. The boiler must be installed on a solid floor. In locating the boiler a 
pallet truck is recommended so as to avoid damage to the casing parts 

 

Health and safety. 

Due to the weight of the boiler, care must be taken when manoeuvring the boiler. HHL 

suggest the use of a pallet truck

 

 

5.2 Water Connections 

 

The connections provided on the boiler (refer to Appendix E and figure 4.4) are suitable for direct connection to 
the system pipe work. However  HHL recommend the use of individual isolating valves, which should be fitted to 
each module to enable isolation from the system. However, the arrangement must comply with the requirements of 

BS 6644.

  

 

When installing water system pipe work, it must be self supporting and care must be taken to ensure that undue 
stress is avoided on the boiler flow and return connections. It is recommended that unions are fitted local to the 
boiler and outside of the casing, to permit future servicing requirements. 

 

 

Each module is fitted with safety valve rated at 6bar. The valve discharge pipe is routed to the rear of the boiler, 
where it must be piped to discharge via a tundish (not HHL supply) suitably located for ease of visibility. 

 

The Fleet is designed to operate at 20°C 

T across the flow and return. Should the flow rate drop, the boiler 

controls will modulate the burner to maintain 20°C 

T. The boiler module is fitted with a single speed circulating 

pump and flow is controlled through a balancing valve, which must be checked and set during commissioning. As 
a safety precaution, a flow switch is fitted to the boiler heat exchanger to shut the system down in the event of 
sudden adverse flow conditions.   

 

Where using Hamworthy Heating Ltd pipe work kits, assembly of these is detailed in Instruction Manual 
500005134 supplied with kit.

 

 

5.3  Flue Connection 

 

5.3.1   

The Hamworthy Fleet V series boiler is designed for use with open flue systems type B23 - Intake from ventilated plant room 
and discharge via horizontal/vertical flue. 
For all B23 installations the Hamworthy supplied air inlet filter (Pt. No. 532812 008) 

MUST

 be used  

1. With the boiler in its desired location, loosely engage the  flue collector ducts into each other and position such 
that the spigots will fit into the respective flue sockets at the rear of the boiler.  
In assembling the flue ducts, it is advisable to lubricate the seal located in the socket fittings using the gel 
provided, to enable easy movement and adjustment. 
2. 

Fit and secure the bottom closing plate to the base of the duct assembly. 

 

Do not fit the flue manifold  

at this stage as it may restrict access to the other connections. 

 

Note: 

Should modules be arranged in banks of 2 or 3 high, adjacent to each other, it is advisable to fit the water 

and flue connections to each individual bank prior to fitting the connections to the adjacent bank(s).

 

 

Flue systems should be designed with reference to 

BS 5440

 

part 1

,  

IGE/UP/10

 and 

Third Edition of the 1956 Clean Air 

Act Memorandum. 

 

To comply with the requirements of the Clean Air Act 1956 a maximum of 150 kW  may be terminated with 
horizontal flue discharges. 

 

Equivalent lengths for 90° bends and 45° bends are given in Appendix C.

 

Содержание F40V

Страница 1: ...or Heating Domestic Hot Water Installations Installation Commissioning and Operating Instructions Models F40V F50V F60V F70V F85V F100V F125V F150V NATURAL GAS I2H IMPORTANT NOTE THESE INSTRUCTIONS MU...

Страница 2: ......

Страница 3: ...Y I2H PLEASE ENSURE RELEVANT INFORMATION REQUIRED WITHIN DOCUMENT IS FOUND BEFORE FIRING BOILER COUNTRY OF DESTINATION UNITED KINGDOM REPUBLIC OF IRELAND THIS BOILER COMPLIES WITH ALL RELEVANT EUROPEA...

Страница 4: ...1 General 5 2 Water Connections 5 3 Flue Connections 5 4 Electrical Connections 6 0 PRE COMMISSIONING 13 6 1 Gas Supply 6 2 Ventilation 6 3 Pipework Valves and Pump 6 4 Flue 6 5 Electrical 7 0 CHECKS...

Страница 5: ...7 6 Combustion analyser probe position 18 Figure 7 6 1 Adjusting gas valve throttle 19 Figure 7 6 2 Adjusting gas valve throttle 19 Figure 7 6 3 Adjusting gas valve offset 19 Figure 7 6 4 Adjusting ga...

Страница 6: ...igure B1 3 Sensor resistance values 46 Figure C1 Flue Data 47 Figure C6 1 Flue equivalent lengths 49 Figure C6 2 Flue Accessories 49 Figure D1 Mechanical Ventilation Flow Rates 50 Figure E1 Water Data...

Страница 7: ...ater for these premises via an indirect cylinder 1 3 4 The Fleet has a low water content and is fitted with an integral circulating pump to ensure that water flow rates are achieved refer to Appendix...

Страница 8: ...kept upright during handling Care must be exercised to avoid toppling the boiler as this will result in damage The flue manifold connecting the vertical modules is supplied separately to the boiler r...

Страница 9: ...separately from the boilers All ancillary items such as isolation valves and boiler make up connectors are factory fitted and tested The whole is shrink wrapped for security and basic protection Refe...

Страница 10: ...icient access at sides and behind boiler for pipe work connections See Figure 3 1 Figure 3 1 1 Dimensions and clearances 750 crs 950 min clearance 700 800 F125 150V 650 F40 100V 700 A 1 43 5 2 0 40 7...

Страница 11: ...N DN80 600 750 750 120 Figure 3 1 2 Table Dimensions and clearances BOILER MODEL Dimension F40V F100V A 580 580 680 680 B 320 320 320 350 C 150 150 150 200 F125V F150V Two high Three high Two high Thr...

Страница 12: ...LTD 6 FLEET V series 500001213 G Figure 3 2 2 F125 150V water pipe work kit 3 high boiler installation shown 750 620 750 360 120 FLOW DN125 GAS R2 RETURN DN125 130 750 120 396 656 786 1 2 BSP Socket f...

Страница 13: ...room must have sufficient space for installation of boilers pipe work pumps controls flues ventilation access and servicing and other items of plant 4 2 Gas Supply Gas supply pipes must be in accordan...

Страница 14: ...to appendix C Any stabiliser fitted must be in or close to the vertical chimney Due to the low flue gas temperature 50 C condensation will occur in the flue flue materials must be non corrosive and ut...

Страница 15: ...event that the system design pressure is lower than the boiler maximum operating pressure according to the requirements of BS6644 2011 The Fleet boiler has an aluminium heat exchanger It is a requirem...

Страница 16: ...tenance is carried out by Hamworthy Heating Limited or a competent maintenance company the maintenance regime detail shall be provided in writing when required to prove compliance with the operating a...

Страница 17: ...ntifreeze plus protection agent Fernox Restorer cleaning agent for removing rust lime and sludge Protector protection agent F1 protection agent The following applies to system design In order to avoid...

Страница 18: ...ot copper Hamworthy recommend plastic waste pipe Condense may be discharged to a standard drain subject to National or Local regulations Location of condense pipe work should prevent freezing within t...

Страница 19: ...modules stop start circuit 24V DC Any interlock circuit must be in series with the time control for each circuit The interlock circuit must never be used to isolate the boiler electrical supply ADDITI...

Страница 20: ...quirements Each module is fitted with safety valve rated at 6bar The valve discharge pipe is routed to the rear of the boiler where it must be piped to discharge via a tundish not HHL supply suitably...

Страница 21: ...ificates should be available for viewing 6 2 Ventilation Ensure that ventilation and air supply to plant room is correct 6 3 Pipe work Valves and Pump Ensure that System flushing and suitable water tr...

Страница 22: ...d with a single speed circulating pump and flow is controlled through a balancing valve which must be checked and set during commissioning As a safety precaution a flow switch is fitted to the boiler...

Страница 23: ...nd a dynamic reading The dynamic reading cannot be taken until the boiler has been started refer to 7 4 A maximum difference in gas pressure of 1 mbar must not be exceeded between static and dynamic c...

Страница 24: ...lose the gas valve The boiler should shutdown after approximately one second and attempt a re ignition Check that the flame has been extinguished 2 Alternatively the flame probe lead can be removed fr...

Страница 25: ...0V F50V F60V F70V Models F85V F100V F125V F150V 4 If combustion is outside of the ranges defined below the factory sealed valves may be adjusted using the following procedure High Fire Target Nat Gas...

Страница 26: ...e relevant boiler settings specific to the installation 7 7 Setting the flow rate to achieve 20 C T Before commissioning is complete the flow rate must be checked and adjusted A ball valve is located...

Страница 27: ...vision active too little flow through boiler 7 7 User Instructions When the boiler is fully commissioned the owner or their representative should be made aware of the lighting up and operating instruc...

Страница 28: ...rheat Thermostat HT Spark Generator Combustion Fan Air Pressure Switch Fuse Water Flow Switch 230v Mains Supply IEC Mains Outlet Socket LMU Control Clip in Module Vfc 0 10v Display Screen On Off switc...

Страница 29: ...refer to figure 8 2 1 1 A change on the information level can be made at any time by pressing the Info button Additional pushes of the Info button will deliver the following data sequence provided by...

Страница 30: ...M C 4 RelModLevel Relative output C 5 Pumpe_PWM Pump setpoint PWM Not used C 6 ek0 Control differential C 7 C8 C9 Reserved Setpoints Service level d 0 Reserved d 1 Tsoll Setpoint of 2 position or modu...

Страница 31: ...HAMWORTHY HEATING LTD 25 FLEET V series 500001213 G Figure 8 2 1 3 Operation and display philosophy...

Страница 32: ...g of symbols Display of dhw temperature or dhw heating active not used Display of boiler or room temp set point or space heating active Display of outside temperature Operational level Normal Operatio...

Страница 33: ...t display If no button is pressed for about 8 minutes the screen will automatically return to the default display Figure 8 2 3 2 Display of Status Code When a status code is displayed the display 1 sh...

Страница 34: ...2 4 Display of lockout code 304 7494z35 0202 8 2 5 Adjusting the heating circuit setpoint temperature Press the flow temperature button to adjust the heating circuit setpoint Press to adjust the requi...

Страница 35: ...14 Time program HC1 switch off time 2nd period 00 00 24 00 hh mm 10 min 24 00 15 Time program HC1 switch on time 3rd period 00 00 24 00 hh mm 10 min 24 00 16 Time program HC1 switch off time 3rd peri...

Страница 36: ...Heating circuit operating modes The control provides 4 different heating circuit operating modes for LMU heating circuit 1 They can be directly selected depending on the requirements see figure 8 2 9...

Страница 37: ...the return sensor provide overheat protection as follows If the first level temperature is exceeded a fault code is displayed If the second level temperature is exceeded an alarm code is displayed an...

Страница 38: ...the boiler to cool and reset thermostat Investigate cause of overheating see section 9 3 113 Flue gas supervision equipment has cut out 117 Water pressure too high 118 Water pressure too low 119 Wate...

Страница 39: ...temperature required to raise the maximum operating temperature possible from the individual boiler modules As standard the boiler modules leave the factory with a maximum operating temperature of 85...

Страница 40: ...HAMWORTHY HEATING LTD 34 FLEET V series 500001213 G Figure 8 3 11 Operating phases...

Страница 41: ..._TSA1_2 PH_TSA2_2 10 Heating operation PH_TI PH_MODULATION Heating mode 11 DHW operation PH_TI PH_MODULATION DHW mode 12 Parallel operation of space heating and DHW heating PH_TI PH_MODULATION Heating...

Страница 42: ...r overheating The most common cause of overheating is lack of water flow rate through the boiler possibly caused by a faulty pump or blockage in the heat exchanger circuit due to system debris Figure...

Страница 43: ...A DISPLAY KEYPAD MODULE FLAME IONISATION PROBE 2 1 1 3 230V 0V HT 1 2 1 3 C 1 2 HT ELECTRODE GAS VALVE SPARK GENERATOR SAFETY LIMIT THERMOSTAT 2 3 L N N L 3 2 1 1 DC FAN PUMP 2 3 3 2 1 1 BLUE BROWN BL...

Страница 44: ...he burner tube can be washed using a soapy water solution Tap the burner flange firmly downwards on a block of wood to dislodge any residual debris from inside the burner tube A damaged or cracked bur...

Страница 45: ...HAMWORTHY HEATING LTD 39 FLEET V series 500001213 G Figure 10 2 Combustion Chamber A A B B Figure 10 2 1 Spark Electrode position Figure 10 2 2 Flame Probe position...

Страница 46: ...nce of the sensor against Figure B 1 3 In refitting the sensor a sealant will be required on the threads Check for water soundness before firing the boiler 11 3 Flue Gas sensor Part no 533901549 The f...

Страница 47: ...models reassemble in reverse order using new gaskets and check all joints for gas soundness 11 8 Main control pcb LMU refer to spares list The LMU is located on the electrical control panel which is...

Страница 48: ...ntrol Valve F40V F70V 533903040 Gas Control Valve O ring F40V F70V 531299051 Gas Control Valve F85V F150V 533903044 Gas Control Valve O ring F85V F150V 742111245 Combustion Fan F40H F70H 533901376 Com...

Страница 49: ...iler Output kW maximum non condensing 80 60 C kW 108 2 162 3 126 4 189 6 Boiler Output minimum 80 60 C kW 10 8 10 8 12 6 12 6 GAS DATA per boiler module F40V F50V F60V F70V Gas Inlet Connection Pipe T...

Страница 50: ...only serve the boiler 4 Multiple modules It is highly recommended that each boiler is connected via its own mains isolator to facilitate servicing and maintenance of the individual boiler whilst leav...

Страница 51: ...21 22 21 22 21 22 15 16 15 16 15 16 External Control Optional External Control Boiler 1 Terminal Rail Boiler 2 Terminal Rail Boiler 3 Terminal Rail 0 10V 0 10V 0 10V Control Signal 0 10V or Enable Not...

Страница 52: ...4 145 0 206 10 0 55047 70 0 1753 150 0 183 5 0 42158 75 0 1481 155 0 163 0 0 32555 80 0 1256 160 0 145 5 0 25339 85 0 1070 165 0 130 10 0 19873 90 0 915 170 0 117 15 0 15699 95 0 786 175 0 105 20 0 12...

Страница 53: ...al section should have a maximum slope of 3 upwards in the direction of the exhaust gas flow All joints should be such that any condensation is directed back down the slope to an open drain connection...

Страница 54: ...exposed position and be so situated as to prevent the products of combustion entering any opening in a building Where the flue diameter is less than 204mm 8 diameter a terminal must be fitted Where t...

Страница 55: ...ing 150 532511174 200 532511175 Pitched roof flashing 150 universal 25 45 532511178 200 23 27 532511179 200 33 47 532511180 200 48 52 532511181 Fixing brackets 150 532511033 200 532511186 Figure C6 2...

Страница 56: ...on in the event of ventilation fan failure 2 Mechanical inlet and mechanical extract can be utilised providing the design extraction rate does not exceed one third of the design inlet rate 3 Mechanica...

Страница 57: ...ry circuits to be connected to the header Figure E1 1 1 on the following page show typical layouts 5 Ideally individual valves should be fitted to each module to enable isolation from the system howev...

Страница 58: ...w the boiler is fitted with an integral flow switch Particular attention should be paid to the restriction of external flow circuits during periods of low heat demand Each boiler module is fitted with...

Страница 59: ...ble valve check Expansion Air Vent Automatic Valve Drain valve valve Drain Boiler Output Feed mm Vent mm 60 150kW 25 32 150 300 kW 32 38 300 600 kW 38 50 601 KW 50 65 Figure E1 4 Cold Feed and Vent Pi...

Страница 60: ...ral pump performance curves 0 1 1 2 2 3 3 4 5 Q m h 3 Model F 40W F 50W F 60W F 70W Model F 85W F 100W F 125W Model F 150W 0 4 1 0 0 2 0 3 0 4 0 5 0 6 0 1 2 2 0 2 8 3 6 4 4 Head m Head m Head m 6 0 6...

Страница 61: ...triple circuit low loss header Non HHL supplied single circuit low loss header Non HHL supplied plate heat exchanger separated system AAV Drain Dosing Pot Note secondary circuit components are not su...

Страница 62: ...hold both up and down arrow keys for at least five seconds to enter advanced parameter list H90 displayed top right of HMI screen Use either up or down arrow key to scroll through the parameter list...

Страница 63: ...HAMWORTHY HEATING LTD 57 FLEET V series 500001213 G NOTES...

Страница 64: ...HAMWORTHY HEATING LTD 58 FLEET V series 500001213 G INSTALLER SITE ADDRESS BOILER TYPE BOILER SIZE S UNIT NO S SERIAL NO S FLUE USEFUL USER INFORMATION...

Страница 65: ...Please complete the information on the Registration Card cut out and return to Hamworthy Heating Ltd...

Страница 66: ......

Страница 67: ......

Страница 68: ...0 fax 0151 647 8101 Southern Ireland Sales Service HEVAC Limited Naas Road Dublin 12 Ireland tel 00 353 141 91919 fax 00 353 145 84806 Northern Ireland Sales Service HVAC Supplies Limited Unit A6 Darg...

Отзывы: