HG2200/HG2200AT Operator’s Manual
Inspect Site
54 - Prepare
Select Installation and Bursting Pit Locations
Consider the following when selecting pit locations:
Slope
Unit should be parked on a level site. Consider how slope will affect unit setup and operation. Assess the
risks on each slope to determine if factors affecting risks create an unsafe condition for pipe bursting.
Traffic
Vehicle and pedestrian traffic must be a safe distance from pulling equipment. Allow at least 10’ (3 m)
buffer zone around equipment.
Space
Check that starting and ending points allow enough space for installation and bursting pits. See “Dig
Check that installation area has enough space for product to be installed.
Check that there is enough space to work.
Access
Consider shade, wind, fumes, and other site features.
Содержание HG2200
Страница 1: ...TECHNICAL PUBLICATIONS Operator s Manual HG2200 HG2200AT Issue 2 1 960 1119 Original Instruction ...
Страница 51: ...HG2200 HG2200AT Operator s Manual Battery Disconnect 50 Controls ...
Страница 75: ...HG2200 HG2200AT Operator s Manual Retrieve Tracked Unit 74 Transport ...
Страница 87: ...HG2200 HG2200AT Operator s Manual Finish Installation 86 Burst Pipe ...
Страница 129: ...HG2200 HG2200AT Operator s Manual As Needed 128 Service ...
Страница 133: ...HG2200 HG2200AT Operator s Manual Declaration of Conformity Information 132 Specifications ...
Страница 136: ...HG2200 HG2200AT Operator s Manual Service Record 135 Service Record Service Performed Date Hours ...
Страница 137: ...HG2200 HG2200AT Operator s Manual 136 Service Record Service Performed Date Hours ...
Страница 138: ...HG2200 HG2200AT Operator s Manual Appendix 137 Appendix Chapter Contents Tire Safety Information ...
Страница 146: ......