Start-up
WARNING
Risk of injury due to the escape of a potentially explosive atmosphere consisting
of dust/air mixtures
ü
Operation with the cover open is prohibited.
1. Before opening the cover, ensure that no potentially explosive atmosphere exists.
2. Do not operate the control outside the electrical, thermal and mechanical characteristics.
1. Use the rating plate to check the supply voltage for which this control is suitable: 115 VAC
and 230 VAC or 24 VDC.
2. Check that the control is connected correctly according to the connection plan.
3. Check whether the correct microfuse is inserted.
4. Apply the supply voltage according to the rating plate.
5. Use the potentiometer to set the required pause and pulse time according to the filter
manufacturer’s data. The upper potentiometer sets the pause time, the lower poten-
tiometer sets the pulse time.
6. Check for correct actuation of the valves.
7. Following completion of the commissioning, screw the cover back on and check the cable
entries. Cable entries that are not required must be sealed with a plug.
Overview of the wire bridges
Wire bridges for 230 VAC (as-delivered condition)
Wire bridges for 115 VAC
5 | Start-up
Operation manual
Electronic solenoid valve control · V1.0 · 04/2022