C.3.2
Connection of air and water supplies
IMPORTANT
This operation requires the involvement of a QUALIFIED TECHNICIAN able to carry out and check
correct connection in observance of current safety regulations:
(analog C.3.1)
Ensure that the whole system is not supplied by electrical, air and water sources.
Ensure all the plant providing the equipment corresponds with its own specifications.
Connect the pneumatic source as shown in Figure 8.
Connect chiller and water tank according to Figure 4. Fill the water tank with water.
If no chiller and water tank (optionals) are used, connect the water source corresponding to Figure 7.
Ensure the water connections are well sealed and that any leaks that could occur do not come into
contact with electrical parts.
C.3.3
Electrical connection
IMPORTANT
This operation requires the involvement of a QUALIFIED TECHNICIAN able to carry out and check
correct connection in observance of current safety regulations:
(s. oben - analog C.3.1)
Ensure that the whole system is not supplied by electrical, air and water sources.
Ensure all the plant providing the equipment corresponds with its own specifications.
Connect electrical power to the press bank as shown in Figure 8. The control panel is left to be
assembled according the needs (height, arrangement) of the user.
For the connection of the chiller see separate instruction.
Ensure the water connections are well sealed and that any leaks that could occur do not come into
contact with electrical parts.