Lifting Instructions
Greenheck's Vertical Fan Coil (VFCD) can be
moved a round a job site on a wheeled cart or
with a forklift. Avoid twisting or uneven lifting of
equipment. Do not lift equipment by coil
connections or headers. The unit must remain
upright during lifting. All access doors and panels
must be closed during lifting to avoid damage.
Mounting Instructions
The VFCD should be mounted on a field supplied base as shown in Figure 2. An optional Greenheck supplied 6
inch extended base may be used when mounting as shown in Figure 3.
The VFCD is available with both
external neoprene and spring isolation options.
2
1.
Fan Section
2.
Coil Section
Chilled Water or DX Coils
Hot Water or Steam Coils
3.
Inlet Filter
Vertical inlet filter with
1
⁄
4
turn fasteners
(Removed for internal viewing)
4.
Side Access Panels
Right and left access to each unit
(upper panel hinged open)
5.
Knockout for recommended
electrical wiring penetration or
disconnect switch.
1
2
3
4
Airflow
5
Airflow
Figure 3
Figure 2