Connect the CT clamps & voltage wires to the current & voltage
input terminals
Before installation, please connect the CT clamp wires to the current input
terminal following the sequence 1S(red) 1L(black) 2S(red) 2L(black). Then connect
the voltage wires to the voltage input terminal following the sequence L(red)
N(black).
At the bottom of the current transformer, there is “K
→
L” indication mark.
Before you clip on the CT over the power line, please make sure the power
current flow direction follow the “K
→
L” indication mark on the CT
GREEN POWERLINK On-Line Energy Management Solution V1.0
8
GREEN POWERLINK On-Line Energy Management Solution V1.0
9
Wiring Diagram
Refer to the following wiring diagram and dial the mode switch that matches
your electrical panel type. Then install CT clamp over the power line and
voltage wires to L and N voltage terminals.
Once the CT smart meter is installed in the electrical panel, turn on the main
breaker and perform initial energy gateway and CT smart meter pair up (see
the operation instruction).
K
L
Botton view
1 Phase & 2 Wire – 1CT