(10) Drain pipes should have a downward slope of at least 1%~2%, in order to
prevent pipes from sagging, install hanger bracket at intervals of 1000~1500mm
(39-3/8~59in.).
Fig 4.3.10
4.3.3 Test of Drainage System
(1) Please test drainage system after electric work is finished.Inject approximately 1L
purified water to drain pan from air vent, ensure that not to splash the water over
the electrical components (e.g. water pump. etc).
(2) During the test, please carefully check the drainage joint, make sure no any
leakage occur.
(3)
It’s strongly recommend to do the drain test before ceiling decoration.
Fig 4.3.12