Levelling the base frame
After the anchor filling mortar is completely cured
the frame should be levelled with a space
between block and lower frame flange of 3 - 5
mm. This space largely depends on the sort of
grout or mortar used. Determine this space as
given in the instructions of the grout or mortar
supplier. This space is necessary for levelling using
the base frame adjusting bolts with metal washers
(supplied separately). The base frame should be
levelled on each frame side. Adjust the frame on
each adjusting place until all frame sides are
horizontal.
•
Finishing with a self-levelling grout (See figure A1.5)
After levelling is completed the adjusting bolt
ends must be greased to avoid bonding to the
self-levelling grout. The space between concrete
block and frame must be completely filled with
the self-levelling grout to ensure that the
complete bottom surface of the base frame will
be supported. Therefore, it is not allowed to use
shims between concrete base and base frame.
Grouting must be carried out in accordance with
the instructions provided by the grouting supplier.
After complete de-aeration of the grouted layer,
secure the base frame by tightening the anchor
bolt nuts and remove all adjusting bolts. At this
stage the drive system can be installed. These
(accessories) installation instructions can be found
in the order manual.
A1.5 Connecting to refrigerating system pipe-
work
After the compressor (package) has been levelled
and secured to the foundation, the system piping
may be connected. The suction line(s) and
discharge line(s) should be installed and supported
such that there is no load exerted on the
compressor. The size and location of the suction
and discharge connections, can be found in the
"Engineering Data" (bare compressor) and in case
of a package, the package lay out drawing.
Fig. A1.5 Grouting details
1 Self-levelling grout
2 Adjusting bolt (4x)
3 Washer
4 Temporary barrier strip around and inside frame
5 Complete cured concrete block
6 Grout layer
Refrigeration Division
Grasso
A : I N S T A L L A T I O N A N D P R E P A R A T I O N F O R U S E
v001.99.01.en
Installation and Maintenance Manual RC(U)6
A1.5
Содержание RC6
Страница 1: ...RC U 6 Installation and Maintenance Manual 00 89 238 v004 00 02 en ...
Страница 10: ...Refrigeration Division Grasso TABLE OF CONTENTS IV Installation and Maintenance Manual RC U 6 v001 99 01 en ...
Страница 24: ...Refrigeration Division Grasso TABLE OF CONTENTS B II Installation and Maintenance Manual RC U 6 v001 99 01 en ...
Страница 36: ...Refrigeration Division Grasso TABLE OF CONTENTS C II Installation and Maintenance Manual RC U 6 v001 99 01 en ...
Страница 60: ...Refrigeration Division Grasso TABLE OF CONTENTS D II Installation and Maintenance Manual RC U 6 v001 99 01 en ...
Страница 64: ...RC6 3 RC6 4 Refrigeration Division Grasso STANDARD ILLUSTRATED PARTS LIST RC6 C4 RC6 0089238 v004 00 02 en ...
Страница 67: ...RC6 5H RC6 5L Refrigeration Division Grasso STANDARD ILLUSTRATED PARTS LIST RC6 0089238 v004 00 02 en RC6 C7 ...
Страница 68: ...RC6 6 RC6 7 Refrigeration Division Grasso STANDARD ILLUSTRATED PARTS LIST RC6 C8 RC6 0089238 v004 00 02 en ...
Страница 71: ...RC6 8 RC6 9 Refrigeration Division Grasso STANDARD ILLUSTRATED PARTS LIST RC6 0089238 v004 00 02 en RC6 C11 ...
Страница 79: ...RC6 1A PARTS LIST RC6 ACCESSORIES Refrigeration Division Grasso v002 99 05 en RC6 Accessories 3 ...
Страница 83: ...RC6 3A PARTS LIST RC6 ACCESSORIES Refrigeration Division Grasso v002 99 05 en RC6 Accessories 7 ...
Страница 84: ...Refrigeration Division Grasso PARTS LIST RC6 ACCESSORIES Accessories 8 RC6 v002 99 05 en ...
Страница 85: ...Refrigeration Division Grasso ...