Before Installing
10
311163ZAH
Before Installing
Uncrating Equipment
Uncrate the SaniForce BES as follows:
1. Inspect the crate for shipping damage. Contact the
carrier if damaged.
2. Remove plywood sides and top of crate.
3. Check the contents for loose or damaged parts.
4. Compare the packing slip against items inside the
crate. Immediately call your Graco distributor about
any shortages or damage.
5. Remove the band strap holding the cylinder bin to
the frame.
6. Remove and unpack the air cylinder bin and pumps
(if applicable).
NOTE:
See your system component manuals to
become familiar with system components and general
operation.
Location
When selecting a location, make sure the location:
•
Is close to where the fluid is being delivered to mini-
mize back pressure and maximize flow rate.
•
Provides enough room around the equipment for
maintenance.
•
Does not interfere with opening the pneumatic con-
trol panel door or frame door (on one or both sides).
If the frame is rotated 180°, the frame door will open
from left to right or from right to left.
•
Provides enough room on the right and/or left side
of the SaniForce BES to easily load and unload fluid
bins with a forklift or pallet-jack hand truck.
•
Provides easy and safe access to the air supply
shutoff valves and the pneumatic control panel.
Graco recommends a minimum of 3 ft (0.91 m) of
open space in front of the panel.
•
Provides enough overhead clearance (11 ft, 3.4 m
recommended) for installing and servicing the air
cylinder and connecting air supply lines to the pneu-
matic control panel.
•
Has a flat, level floor.
Moving Frame to Location
•
Do not remove the frame from the pallet at this time.
•
Use a forklift or hand truck and support devices,
such as a hoist, and have an adequate number of
personnel to move the frame to the installation site.
•
Avoid jarring or tilting the frame while moving it.
NOTE:
•
Ensure there is an adequate compressed air supply.
Refer to air motor/pump manual for your pump air
consumption. About 250-300 scfm at 100 psi (0.7
MPa, 7 bar) is required to operate the pumps at the
maximum rate.
•
Have all component manuals available for specific
component requirements.
•
Ensure that all hoses are properly sized and pres-
sure rated for the system.
NOTICE
Moving the SaniForce BES off the pallet without follow-
ing this uncrating procedure will damage equipment.
The frame is shipped with several major components
attached and weighs about 2500 lb. (1134 kg). To
avoid injury and equipment damage, follow
instructions below. Never have one person move or
lift the frame.