6 Commissioning

Fit the outer case, secure with the screws previously removed.

Make sure that the pilot is alight and stable, view through
window “G”.

Set the control thermostat knob “A” between “MIN” and “MAX”
(“MAX” is about 82

o

C (180

o

F) and check that the burner lights

smoothly.  Check all gas connections for soundness with a
suitable leak detection fluid.

Note. Should the boiler fail to operate correctly refer to Fault
Finding Section.

To set the burner pressure operate the boiler for 10 minutes,
remove the gas valve cover, if not already removed, adjust the
gas pressure by screw “H” until the required pressure is obtained,
see the relevant Table 1 for setting pressures.

Stick the self adhesive arrow, from the loose items pack, in the
appropriate space beneath “MIN” and “MAX” column on the
data label.

Should any doubt exist about the gas rate this should be
checked at the meter, using a stop watch to time at least one
cubic foot of gas consumption.

Replace the gas valve cover.

Remove the pressure gauge and refit the screw, make sure that
a gas tight seal is made.

6.4 Testing

Check the operation of the flame failure device on the boiler to
make sure that the gas valve shuts down within 60 seconds,
indicated by a “click” from the valve.

MODEL AND SERIAL
NUMBER PLATE

A

K

L

G

H

B

J. (Shown Off)

C

A. CONTROL THERMOSTAT KNOB
B. GAS CONTROL KNOB
C. IGNITER BUTTON
G. VIEWING WINDOW
H. GAS RATE ADJUSTMENT SCREW

(UNDER COVER SCREW)

J. GAS SERVICE COCK
K. PRESSURE TEST POINT
L. PILOT BURNER

ADJUSTMENT SCREW

M. FLUE BLOCKAGE SAFETY DEVICE

RESET SWITCH

M

Diagram 6.1

5354

6.5 Flushing

Allow the system to reach maximum working temperature and
examine for water leaks.

The boiler should then be turned off and the system drained as
rapidly as possible whilst still hot.

Refill the system and vent and check for water soundness as
before.

6.6 Adjustment - All Systems

When commissioning the system the boiler should first be fired
on full service, that is, central heating and domestic hot water.
The system should then be balanced, adjusting the pump and
lockshield valve as necessary.  Having achieved a satisfactory
condition operate the boiler with the bypass fully closed on
minimum load, normally this will be central heating with one
radiator, in the main living area working.  The valve should then
be gradually opened to achieve a flow rate of 7.8L/min (1.7gal/
min).

Under  no  circumstances  should  this  valve  be  left  in  the  fully
closed position.

Operate the boiler again on full service and check the balancing,
making further adjustments as necessary.

If thermostatic radiator valves are fitted care must be taken to
make sure adequate flow through the boiler when they close,
refer to the current issue of BS7478.

Do not attempt to adjust the thermostat calibration screw.

Test the boiler for spillage of the flue products at the draught
diverter as detailed in the current issue of BS5440 Part 1.  See
also Section 2.3.

Содержание economy plus c 30

Страница 1: ...Customer Service number 01773 828100 Our Guarantee gives you peace of mind plus valuable protection against breakdown by covering the cost of Guarantee Registration Open Flue Boiler This is a Cat I2H...

Страница 2: ...uels 2 Directive 73 23 EEC on the harmonization of the Laws of the Member States relating to the electrical equipment designed for use within certain voltage limits 3 Directive 89 336 EEC on the appro...

Страница 3: ...freezing up If an immersion heater is fitted in the domestic hot water cylinder make sure that it is switched off If you have a sealed water system you should contact your installer servicing company...

Страница 4: ...ckage safety device may also need resetting refer to safety device instructions Make sure that the pilot is alight and stable Switch on the electrical supply to the boiler Check that all external cont...

Страница 5: ...ons applicable in Scotland local Water Company Byelaws The HealthandSafetyatWorkAct ControlofSubstancesHazardous to Health The Electricity at Work Regulations and any local applicable regulations Deta...

Страница 6: ...VC flexible type to the current issue of BS6500 Table 16 not less than 0 75mm2 24 0 20mm 1 9 Draining Tap A draining tap must be provided at the lowest points of the system which will allow the entire...

Страница 7: ...moval of the boiler Where the boiler is fitted in a cupboard or compartment permanent high and low level ventilation must be provided The minimum ventilation areas required are given in Table A 2 2 Bo...

Страница 8: ...ations for the best product to use When installing a boiler in an existing system whether or not using an inhibitor take special care to drain the entire system including the radiators then thoroughly...

Страница 9: ...em that is the height of the highest point of the system above the expansion vessel The water capacity of the boiler is given in Section 1 3 7 Pressure Gauge A pressure gauge with a set pointer and co...

Страница 10: ...the domestic hot water cylinder Alternatively provision for make up can be made by using a filling loop 3 10 Filling a Sealed Water System Provision for filling the system at low level must be made T...

Страница 11: ...cable clamp When making connections make sure that the earth conductor ismadeofagreaterlengththanthecurrentcarryingconductors so that if the cable is strained the earth conductor would be the last to...

Страница 12: ...N L N BROWN BLUE GRN YEL GAS VALVE BROWN BROWN RED RED PURPLE BLUE BROWN BLUE GRN YELLOW CHASSIS EARTH POST 3 7 6 8 9 Remove Red Link between 9 and SL when fitting a time control etc If link is not re...

Страница 13: ...R BUTTON G VIEWING WINDOW H GAS RATE ADJUSTMENT SCREW UNDER COVER SCREW J GAS SERVICE COCK K PRESSURE TEST POINT L PILOT BURNER ADJUSTMENT SCREW M FLUE BLOCKAGE SAFETY DEVICE RESET SWITCH M Diagram 6...

Страница 14: ...ice or replacing parts isolate the gas and electrical supplies Unless stated otherwise all parts are replaced in the reverse order to removal 7 1 Heating Body Service Remove the controls cover by pull...

Страница 15: ...ctor manifold Diagram 7 2 ACCESS FOR SERVICING Diagram 7 3 PILOT ASSEMBLY PILOT INJECTOR ADAPTOR OLIVE PILOT TUBING NUT THERMOCOUPLE NUT IGNITION LEAD clear end ELECTRODE THERMOCOUPLE SECURING SCREWS...

Страница 16: ...ownindiagram 7 7 Check the pilot burner flame lengths are as shown in diagram 7 7 7 5 Thermocouple Generally follow the instructions given in Section 7 1 Unscrew the thermocouple nut to release from t...

Страница 17: ...ithdraw the phial see diagram 7 8 Remove the control box by undoing the two fixing screws at the front and lower the front of the box until it is clear of the cover Push the box towards the rear of th...

Страница 18: ...ew s Inset B Carefully remove phial and capillary through back of boiler Inset C Having opened control box remove the electrical connections from the flue blockage safety device the locknut and capill...

Страница 19: ...on maximum control thermostat setting Change faulty overheat cutoff device The correctly set overheat cutoff device operates prematurely There is no air in the heating body and water circulation satis...

Страница 20: ...continuity YES NO NO 8 7 Thermocouple and Overheat Cutoff Device To test the thermocouple a meter with a range of 0 to 30 mV is required Symptom The pilot burner fails to stay alight Test the thermoc...

Страница 21: ...Device if faulty repair or renew Turn ON thermostat Does main burner light Turn ON thermostat With appliance cold Is there 240V between 7 and N Turn ON thermostat Is there 240V between 7 and N MAIN T...

Страница 22: ...ONTROLS IN ORDER Faulty Cable PURPLE between thermostat and terminal block repair or renew Faulty pump inform customer Faulty thermostat renew YES YES YES NO NO NO YES Continued Continued MAIN TERMINA...

Страница 23: ...TISFACTORY Does pilot flame envelop thermocouple Check aeration If necessary Clean pilot rectify blockage in pilot injector or replace Check thermocouple circuit using Thermocouple and Boiler Overheat...

Страница 24: ...cutoff device 313 064 5 800015 Gas valve assembly inc 14 313 067 6 900000 Thermocouple 394 162 7 203415 Pilot burner inc 12 394 161 8 202600 Electrode 384 149 9 416144 Control thermostat knob 355 401...

Отзывы: