General Assembly Instructions
Actual elevator construction will vary between contractors depending on available equipment,
crew experience and personal preference. However, we suggest the following procedure:
1
Set the boot on the footing.
2
Assemble the head section complete with the work platform, drive components and a
minimum of a 10’ leg section.
3
Position the crane so that the leg and all spouting can be constructed in one set up.
4
Sub-assemble leg sections together in 30’ segments, along with ladder, safety cage and
any platforms. Remember to position the guy wire brackets and cables at 20’ intervals.
Alternate Method - 4.
Some contractors prefer to lift the elevator in 10’ increments and
bolt the leg sections on individually.
5
Raise the elevator and continue to add sub-assembled leg sections until legs are
complete.
6
Securely guy and plumb the elevator.
7
Install the belt and make a temporary splice.
8
Fasten the buckets to the belt and make a permanent splice.
9
Check for loose fasteners and check the operation of the elevator without material.
Note:
Crane time is reduced if approximately 30’ of legging, ladder, etc. can
be attached to the head while it still rests on the ground.
4
Pre-Assembly