3
Sketch 4A
Sketch 4B
1/16
Shim
Sketch 3A
Wall Channel # 19
Base Channel #22
Sketch 3B
Wall Channel # 19
Base Channel #22
Channel #22 is cut to size on factory.
Set the Base Channel #22 on the base and mark holes for screw anchors (
Sketch 3A
).
Remove the channel. Drill all marked holes and, clean the Tub
/
Shower Enclosure ledge and
the Base Jamb areas thoroughly. Insert Wall Anchors #11 into the drilled holes and install Base Channel using
Screws #12 as shown in
Sketch 3B
. Do not apply Silicone Sealant to the back side of the Wall Channel Sealing
the Wall Channel will be completed in the final step.
SAME PLANE
Wall Jamb
Base
Jamb Bumper
Wall Jamb # 3 is cut per size on factory.
Place a 1/16 shim on the corner by opposite wall, where wall jamb#3 will be installed
Position Wall Jamb #3 on top of 1/16 shim (
Sketch 4B
). Make sure that the front face of Base Channel #22
and front face of wall jamb #3 are on the same plane (
Sketch 4A
). Mark locations of wall anchors.
Remove Wall Jamb #3 and drill the marked holes. Clean the Tub/Shower Enclosure ledge and
the Wall Jamb areas thoroughly. Secure Wall Jamb #3 with screws #12 using top and bottom hole.
For middle anchor use screw #26 and Jamb Bumper # 7 .See
Sketch 4B
for detail.
4
1/16” Shim