5
Model: FSH-5
&
FSH-6
Installation
2.
Installation
This section summarizes the procedures necessary to install a new
FSH-5 or FSH-6 Ventless Hood
. Before
continuing, please thoroughly review this Section and any accompanying installation instructions.
Following these procedures and instructions will help to ensure a safe and proper installation.
DO NOT ALTER, ADD ATTACHMENTS OR OTHERWISE MODIFY THIS EQUIPMENT.
IMPORTANT!:
▪
In some cases, it may be necessary to consult with a HVAC contractor and have them confirm that proper
room air exchange is occurring, and that the capability of current on-site air conditioning systems is sufficient
to handle the heat load of any additional cooking equipment.
▪
Exhaust ventilation is recommended for areas in which recirculating Hoods are being operated.
Giles
recommends at least
50 CFM
airflow per linear foot of hood space. This amount could vary based on local codes
and site-specific installation requirements.
▪
The sound level of the Hood when operating is approximately 73 dB’s.
▪
DO NOT
attach any additional ductwork to the Hood’s exhaust outlet. Doing so creates excessive back pressure that will
significantly reduce Hood capture, resulting in unsatisfactory performance.
▪
DO NOT
attempt to direct the Hood exhaust into a ceiling niche or the space above a suspended ceiling.
2.01
Location
1. A minimum clearance of
14” (355.6 mm)
must be maintained between the top of the Hood exhaust outlet and
the ceiling, or other overhead obstructions.
2. For ceiling suspended models, be certain that the intended mounting site is structurally sound and capable of
supporting the Hood’s weight. See
Section 1.04.4, Weights
.
3. Ventless Hoods are intended only for use in relatively large, unconfined, open spaces that have
sufficient fresh
air make-up
.
IMPORTANT!:
It is the responsibility of the Purchaser/Customer to provide the following, not included with Hood purchase:
• Installation materials, both mechanical and electrical, such as necessary mounting hardware, electrical conduit
and wire, conduit connectors, any required additional electrical panels and circuit breakers, etc.
• All installation labor expenses, including building modifications, rental expense for tools/equipment required to
complete installation, etc. It is adviseable to contract a professional kitchen equipment service company to
install the Hood.
• All approvals, permits and fees required by the
Authorities Having Jurisdiction (AHJ)
to authorize use of a
ventless recirculating Hood ... building inspector, fire marshal, health department, etc. Be sure that all approvals
are obtained before proceeding.
• The listed fire suppression system to be connected to the Hood ...
Ansul® R-102 Wet Chemical System
.
Field
installation, set-up, testing and charging must be preformed by an authorized Ansul Distributor/Dealer. Hood is
factory pre-plumbed with piping, conduit, nozzles, and detector brackets, including an exhaust fire damper.
Содержание FSH-5
Страница 2: ......
Страница 4: ......
Страница 30: ...Model FSH 5 FSH 6 Overview 20 5 2 1 ILS Option Only 3 4 3 01 Control Panel ...
Страница 32: ...22 Model FSH 5 FSH 6 Overview 3 02 Filter Chamber Exhaust Not shown 2 7 8 1 5 3 4 6 9 9 ...
Страница 36: ...26 Model FSH 3 5 FSH 4 Overview ...
Страница 38: ...28 Model FSH 5 FSH 6 Operation Filter Maintenance 4 02 2 Baffle Filter Removal Place in OFF position ...
Страница 50: ...40 Model FSH 5 FSH 6 Operation Filter Maintenance ...
Страница 62: ...52 Model FSH 5 FSH 6 Parts List Not shown 7 04 Under Hood Filters Lights 4 5 2 1 3 1 3 ...
Страница 64: ...54 Model FSH 5 FSH 6 Parts List Not shown 7 05 Doors Front Panel Ceiling Suspended Model 7 9 4 2 1 3 6 5 8 10 ...
Страница 68: ...58 Model FSH 5 FSH 6 Parts List ...
Страница 69: ......