Production test and commissioning

6.2.2  Attaching the cover

 

X

Hook the cover (2) with cover fixing (1) on 

the track (3).

The cover may not be swiveled up by more than 

90° during opening. See Chapter 7.1.1 on how  

to remove the cover.

 

X

Swivel the cover downwards and turn it 

into the threaded pin (4).

 

X

Place the leaf springs (5) over the cover 

fixings (1) on the outside: place one leaf 

spring at each of the outermost of the  

two cover fixings.

1

5

 

X

Screw the locking pin for toothed belt locking (option) in again.

Содержание Powerdrive

Страница 1: ...Powerdrive Product family EN Installation and service instructions 192477 01...

Страница 2: ...ting the floor guide 9 5 4 Installing the moving leaf 10 5 5 Mounting the drive components 16 5 6 Installing cable guides 19 5 7 Connecting the tooth belt locking mechanism optional and control unit 2...

Страница 3: ...s to be taken keep to the given order 1 2 Revisions and validity Version 01 valid for Powerdrive product family from model year 2021 1 3 Product liability In compliance with the liability of the manuf...

Страница 4: ...ork must be performed by properly trained personnel authorised by GEZE The country specific laws and regulations are to be observed during safety technology tests If unauthorised changes are made to t...

Страница 5: ...ss breakage Always only use safety glass Risk of injury due to sharp edges on the drive and door leaf Risk of injury during installation through freely moving parts 2 4 Environmentally conscious worki...

Страница 6: ...installation with ISO profile systems The following profiles can also be used in combination with the Powerdrive product family Toughened safety glass clamping fitting Wooden moving leaf Framed movin...

Страница 7: ...poke PL 2 leaf 70485 2 0251 Component drawing Track bespoke PL 1 leaf 70715 9 9872 Installation drawing ISO leaf lock M aluminium secondary closing edge 70715 9 9873 Installation drawing ISO leaf lock...

Страница 8: ...ons made on site by the customer to ensure proper installation Type and load capacity of the fa ade construction or suspending frame Evenness of the installation surface Evenness of the finished floor...

Страница 9: ...6 with 2 suitable countersunk head screws 1 and 2 Angled floor guide with moving leaf right hand slide to open X X Screw in the angled floor guide 6 with 2 suitable countersunk head screws 3 and 2 1...

Страница 10: ...oor guide option For assembly of the continuous floor guide see the Continuous floor guide assembly drawing For further information see the respective installation diagrams Chapter 4 1 5 4 Installing...

Страница 11: ...ION Risk of injury due to a falling roller carriage X X Ensure that the counter rollers are placed correctly when placing the roller carriage X X Swivel the roller carriage 1 into the track from the f...

Страница 12: ...over The moving leaves are very heavy X X At least 2 people should work together to set up the moving leaf WARNING Risk of injury due to glass breakage X X At least 2 people should work together to se...

Страница 13: ...the applicable standards and guidelines on crushing shearing and drawing in spots X X Loosen the 2 screws 2 on the roller carriage X X Adjust the height adjusting screw 1 so that the moving leaves are...

Страница 14: ...st have a vertical clearance of approx 0 5 mm to the track corresponds approximately to the thickness of 4 sheets of copying paper 1 2 approx 0 5 X X Loosen the locknut 1 X X Move the counter roller 2...

Страница 15: ...on the main closing edge side left hand slide to open Driver position at the top on the secondary closing edge side Detailed information can be found on the drive drawing X X Use 2 screws 1 to fix th...

Страница 16: ...belt into the toothed belt locking 5 5 2 Fitting the tooth belt to the driver X X Place the toothed belt locking 1 on the ends of the tooth belt 3 3 teeth per belt end 1 leaf X X Screw the toothed be...

Страница 17: ...otor gear unit X X Tighten the screw 1 torque 10 Nm X X Push the slot head screwdriver into the gap and lever it until the tooth belt is pre tensioned X X Tighten 2 screws 2 torque 15 Nm 5 5 4 Setting...

Страница 18: ...er carriages X X Tighten the setscrews 2 using the Allen key torque 3 Nm 5 5 6 Positioning the tooth belt locking mechanism optional X X Close the moving leaves X X Loosen the screws 1 at the tooth be...

Страница 19: ...m The driver must not come into contact with the tooth belt locking mechanism optional during operation X X After the tooth belt has been installed check click the switching points of the indicator sw...

Страница 20: ...control unit 2 X X Route the cable to the tooth belt locking mechanism optional 5 8 Connecting the transformer ground The track is not earthed if there is a poor connection between earthing jumper 3 a...

Страница 21: ...n and earth conductor test in accordance with VDE 0100 Part 600 X X Remove the sheath of the mains cable 4 on a max of 40 mm 2 3 9 mm PE 9 mm max 30 mm 10 mm 4 X X Strip the mains cable 4 Sheath remov...

Страница 22: ...entire length of the track X X Release the cover carefully and check whether it has been suspended safely X X Unscrew the locking pin 1 from the tooth belt locking mechanism optional 6 2 1 Mounting t...

Страница 23: ...swiveled up by more than 90 during opening See Chapter 7 1 1 on how to remove the cover X X Swivel the cover downwards and turn it into the threaded pin 4 X X Place the leaf springs 5 over the cover f...

Страница 24: ...ectrical installation see wiring diagram X X Mount the operating elements so that users cannot stand in the danger zones 6 5 Commissioning the door system For information about connection and paramete...

Страница 25: ...urface against scratches using suitable means 7 1 2 Checking tooth belt tension X X Put the door into operation The tooth belt must not lift up from the motor gear or skip when braking and acceleratin...

Страница 26: ...r guide area Check for jarring free function X X Clean floor guide area Floor guide area brushes Check for contamination and hardness X X Clean or replace Moving leaf Check for smooth movement X X See...

Страница 27: ...ce if necessary 8 1 2 Replacing roller carriage 1 1 1 1 1 1 1 2 1 1 1 1 1 3 1 1 4 1 1 4 5 X X Secure moving leaf against falling X X Separate driver from roller carriage 3 if necessary X X Loosen nut...

Страница 28: ...nge the track roller 4 torque 20 Nm X X Reinstall roller carriage in reverse order 8 1 4 Replacing brushes X X Secure moving leaf against falling X X Unhook the moving leaf if necessary and tilt it as...

Страница 29: ...connect the door system from the 230 115 V mains supply on site before removing the PCB cover 1 and secure against being switched back on again X X You will find the fuse value on the wiring diagram 1...

Страница 30: ...ion 2 Connection to external safety systems which have been approved by the drive manufacturer 3 Low energy Note Several classes may be marked Safety for automatic door systems version installation se...

Страница 31: ...20 9 Safety devices mounted 6 3 24 10 Switches push buttons installed and correctly connected 6 4 24 11 Programme switch installed 6 4 24 12 Transformer ground fitted 5 8 20 13 230 115 V connection e...

Страница 32: ...geze com www geze fr Hungary GEZE Hungary Kft E Mail office hungary geze com www geze hu Iberia GEZE Iberia S R L E Mail info es geze com www geze es India GEZE India Private Ltd E Mail office india...

Отзывы: