USING THE ELCOSEAL lay-down equipment

Operation:

Sequence of Basic Job Steps

Hazards

Controls/Recommended Safe Work 

Procedure

1

Ensure all lifting equipment is in sound 

order and the chains are not twisted, 

are of equal length and spacing on the 

spreader beam.

Uneven lifting of the roll.

Ensure chains are free and equal.

2

Shackle spreader bar assembly onto 

machine.

Incorrectly attached to plant/

equipment.

Check shackles before lifting.

3

Grease pole with WD40 or similar.

Careful handling of greasy pole.

Personnel to wear gloves 

with extra grip.

4

Insert Pole manually into central core 

of ELCOSEAL® roll.

Don’t look down core from other 

end.  Don’t use machinery to force 

pole through core.

Keep away until pole protrudes.

5

Position spreader beam over, or 

preferably grounded alongside the roll 

to be lifted.

Wind or machine movement causing 

the suspended frame to swing 

around uncontrollably.

If roll needs to be suspended, then 

ensure stability using guide ropes.

6

Attach end collars onto pole and 

tighten locking nuts.

Not adequately tightening locking 

nuts.

Check nuts.

7

Check chain attachment position 

(eyelet) on frame to ensure chains 

hang vertically when roll is suspended.

Chains angle outward (at top of 

chain) tending to pull collars off the 

end of the pole.

Check each roll as the core widths 

(and hence position of the collar) 

may vary slightly from roll to roll.

8

Raise machine arm.

Lifting too fast/tangle chains

Raise in a control manner with no 

personnel to go under lifted roll.

Uncontrolled dispensing of 

ELCOSEAL®.

Do not cut tape (around roll 

diameter) and start dispensing until 

roll is in position and grounded or in 

a stable position over level.

9

Move roll into start position.

Roll/Frame jerking and swinging – 

knocking someone over.

Keep personnel clear or use guide 

ropes so personnel can minimise roll 

swinging without standing beneath 

or near the suspended roll.

10

Place roll in position.

Lowering onto personnel.

Roll must be positioned and 

grounded.

11

Unroll at no faster than walking pace 

by moving the plant in the required 

direction. Avoid taking machinery over 

previously deployed GCL.

Sliding of dispensed material across 

the subgrade and ‘up-ending’ 

personnel following behind on 

dispensed material.

Maintain exclusion zone.

Do not attempt to pull ELCOSEAL® 

off the roll by hand as it is very 

heavy.

Use equipment where possible.

12

Once roll is empty, remove from pole 

from core by loosening collar.  Pole 

can remain in situ.

Removing pole with machine.

Manual operation only.

GEOFABRICS.COM.AU

QUALITY - SUPPORT - EXPERTISE

GEOFABRICS® is a registered trade mark of Geofabrics Australasia Pty Ltd.

SD 4 - 11/12

 

MELBOURNE 

SYDNEY 

NEWCASTLE 

COFFS HARBOUR 

PERTH 

ADELAIDE 

 

 

(03) 8586 9111 

(02) 8785 8800 

(02) 4950 5845 

(02) 6653 5706 

(08) 9249 5411 

(08) 8162 5855  

 

 

Fax: (03) 8586 9186 

Fax: (02) 9821 3670 

Fax: (02) 4950 5895 

Fax: (02) 6653 5706 

Fax: (08) 9249 5447 

Fax: (08) 8162 5755  

 

HOBART 

BRISBANE 

TOWNSVILLE 

BUNDABERG 

GOLD COAST 

DARWIN 

 

(03) 6273 0511 

(07) 3279 1588 

(07) 4774 8222 

(07) 4155 9968 

(07) 5594 8600  

0407 523 669 

 

Fax: (03) 6273 0686 

Fax: (07) 3279 1589 

Fax: (07) 4774 8655 

Fax: (07) 4155 9968 

Fax: (07) 5563 3727 

Fax: (08) 8162 5755

Отзывы: