 6 

• Manual operation handle in the UP position - LOAD terminals 

(T1, T2) are connected to UTILITY terminals (N1, N2).

• Manual operation handle in the DOWN position - LOAD termi-

nals (T1, T2) are connected to EMERGENCY terminals (E1, 

E2).

3.2.2   LSS MANUAL OPERATION

A manual HANDLE is shipped with the transfer switch. Manual 

operation must be checked BEFORE the LSS is operated electri-

cally. To check manual operation, proceed as follows (Figure 3.2):
1.  Turn the generator’s AUTO/OFF/MANUAL switch to OFF.
2.  Turn OFF UTILITY SERVICE DISCONNECT circuit breaker.
3.  Note position of non-essential LSS main contacts by observ-

ing the moveable contact carrier arm. This can be viewed 

through the long narrow slot in the inside cover of the ATS. 

The top of the moveable contact carrier arm is yellow to be 

easily identified.

• Manual operation handle in the UP position - non-essential 

loads OFF.

• Manual operation handle in the DOWN position - non-essen-

tial loads ON.



 Do not use excessive force when operat-

ing the transfer switch manually or damage 

could be done to the manual handle.

3.2.3   CLOSE TO UTILITY SOURCE SIDE

Before proceeding, verify the position of the switch by observing 

the position of manual operation handle in Figure 3.1. If the handle 

is UP, the contacts are closed in the UTILITY (NORMAL) position, 

no further action is required. If the handle is DOWN, proceed with 

Step 1.
Step 1:  With the handle inserted into the moveable contact carrier 

arm, move handle UP. Be sure to hold on to the handle as 

it will move quickly after the center of travel.

Step 2:  Remove manual operating handle from moveable contact 

carrier arm. Return handle to storage bracket.

3.2.4   CLOSE TO GENERATOR SOURCE SIDE

Before proceeding, verify the position of the switch by observ-

ing the position of the manual operation handle in Figure 3.1. If 

the handle is DOWN, the contacts are closed in the GENERATOR 

(STANDBY) position. No further action is required. If the handle is 

UP, proceed with Step 1.
Step 1:  With the handle inserted into the moveable contact carrier 

arm, move the handle DOWN. Be sure to hold on to the 

handle as it will move quickly after the center of travel.

Step 2:  Remove manual operating handle from moveable contact 

carrier arm. Return handle to storage bracket.

3.2.5   RETURN TO UTILITY SOURCE SIDE

Step 1:  Manually actuate switch to return manual operating handle 

to the UP position.

Step 2:  Remove manual operating handle from moveable contact 

carrier arm. Return handle to storage bracket.

Move handle UP for the

UTILITY (NORMAL) position.

Move handle DOWN for the

GENERATOR (STANDBY) position.

Attach handle to the moveable

contact carrier arm.

NOTE:

  Return handle to storage position in enclosure when finished with manual transfer.

Figure 3.1 — Actuating ATS Transfer Switch

Operation

Содержание RTSJ200A3

Страница 1: ...This manual should remain with the unit Owner s Manual LTS Load Shed Switch...

Страница 2: ...infor mation on tags decals and labels that may be affixed to the transfer switch Replace any decal or label that is no longer legible DANGER Connection of a generator to an electrical system normall...

Страница 3: ...hazardous and possibly LETHAL electric shock DO NOT WORK ON THE TRANSFER SWITCH UNTIL ALL POWER VOLTAGE SUPPLIES TO THE SWITCH HAVE BEEN POSITIVELY TURNED OFF Competent qualified personnel should inst...

Страница 4: ...will operate and disconnect the non essential loads which results in a reduction in the load on the generator The third function is a 16 circuit load center to connect the criti cal loads to These lo...

Страница 5: ...switches 1 4 For one shot operation mode set DIP switch 5 to ON Reconnection of the non essential loads will occur one time after the time set on DIP switches 1 4 If DIP switch 5 is OFF the LSC will a...

Страница 6: ...stalling Do not drop the switch Protect the switch against impact at all times and against construction grit and metal chips Never install a transfer switch that has been damaged This transfer switch...

Страница 7: ...rals are to be connected on the busbars mounted on the load center next to the branch circuit breakers 2 6 CONNECTING CONTROL WIRES Control system interconnections consist of N1 N2 and T1 and leads 0...

Страница 8: ...L position no further action is required If the handle is DOWN proceed with Step 1 Step 1 With the handle inserted into the moveable contact carrier arm move handle UP Be sure to hold on to the handle...

Страница 9: ...NOW BEING DELIVERED TO TRANSFER SWITCH TERMINALS CONTACT WITH LIVE TERMINALS RESULTS IN EXTREMELY DANGEROUS AND POSSIBLY FATAL ELECTRICAL SHOCK 7 With an accurate AC voltmeter and frequency meter chec...

Страница 10: ...ual Operation Handle and operating lever of transfer switch should be in UP position 10 Turn on the UTILITY power supply to transfer switch using the UTILITY SERVICE DISCONNECT circuit breaker The uti...

Страница 11: ...9 Notes...

Страница 12: ...10 Notes...

Страница 13: ...11 Notes...

Страница 14: ...12 Installation Diagram 200 Amp Enclosure Drawing 0G8775 B...

Страница 15: ...8 9 B 2 1 3 9 8 7 B D1 A 6 3 4 5 2 1 7 6 3 2 1 4 5 1 2 2 1 3 1 2 3 4 5 6 J4 RL2 D2 1 2 2 1 3 TO LOADS NON ESSENTIAL TOP TERMINALS TO GROUNDING ELECTRODE 194 OPTIONAL ALARM CONTACT CUSTOMER SUPPLIED N...

Страница 16: ...Part No 0H8807 Revision E 08 01 13 Printed in U S A...

Отзывы: