3.1 FUNCTIONAL 

TESTS 

AND

ADJUSTMENTS

Following transfer switch installation and interconnec-

tion, inspect the entire installation carefully.  A compe-

tent, qualified electrician should make the inspection.
The installation should comply strictly with all applica-

ble codes, standards, laws and regulations.  All electri-

cal connections must be correct and in compliance with

applicable codes and standards.
Make sure the standby generator is ready.  This

includes checking engine oil level, coolant level, fuel

supply, batteries and other items specified in the

Owner’s Manual for specific generators.
Complete all functional tests as outlined in the Post

Installation Start-Up Adjustments section.  Do this

before placing the transfer switch into service.
Functional tests of the transfer switch include these

tests:  (a) Manual Operation, (b) Voltage Checks and (c)

Electric Operation.

To avoid damaging the transfer switch, perform
functional test in the exact order given.

Before proceeding with functional tests, read and be

sure you understand all instructions in this section.

Also, read the instructions and information on tags and

decals affixed to the transfer switch.  Note any options

and accessories that might be installed or provided with

the switch and review their operation.

Do not attempt manual operation of the transfer
switch until after all power voltage supplies to
the switch have been turned off.  Failure to turn
off power voltage supplies may result in danger-
ous and possibly fatal electrical shock.

3.2 MANUAL 

OPERATION

Instructions for “V” type transfer switches:  Test manu-

al operation as follows:
1. Check that the generator’s Auto-Off-Manual switch

has been set to the OFF position.

2. Turn Off the UTILITY power supply to the transfer

switch, using whatever means provided (such as the

UTILITY source main line circuit breaker).

3. Set the generator’s main circuit breaker to its Off or

OPEN position.

Failure to turn OFF all power voltage supplies to
the transfer switch before attempting manual
operation results in extremely hazardous and pos-
sibly fatal electrical shock.

4. Remove the manual transfer handle from the enclo-

sure.

5. Place open slot of the manual transfer handle on the

small tab of the transfer switch operating lever

(Figure 3.1).

6. Pull manual transfer handle downward.  If handle is

down, LOAD is connected to STANDBY power

source.  If handle is up, LOAD is connected to UTIL-

ITY power.

7. Move the transfer switch main contact to both posi-

tions several times.  Leave the transfer switch in the

UTILITY position and connect LOAD to the UTILITY

power source (manual operation lever is up).

Figure 3.1 — Transfer Switch Operation (“V” Type)

DANGER

DANGER

!

Section 3 — Post Installation Start-Up Adjustments

Generac 100 Amp Transfer Switch

Содержание 4678-1

Страница 1: ...Owner s Manual 100 Amp V Type Transfer Switch Models 9227 2 4678 1 This manual should remain with the unit...

Страница 2: ...hazard GENERAL HAZARDS Any AC generator that is used for backup power if a NORMAL utility power source failure occurs must be isolated from the NORMAL utility power source by means of an approved tran...

Страница 3: ...e insulative mats over a dry wood platform Work on this equipment only while standing on such insulative mats Never work on this equipment while physically or mentally fatigued Keep the transfer switc...

Страница 4: ...iates re transfer back to NORMAL power source After this re transfer the controller signals to open the start circuit to the generator which shuts down the engine The controller is then armed and read...

Страница 5: ...tortion level all mounting points If nec essary use washers behind mounting holes to level the unit 2 4 CONNECTING POWER SOURCE AND LOAD LINES Make sure to turn OFF both the normal Utility and standby...

Страница 6: ...rly supported of approved insulative qualities protected by approved conduit and of the correct wire gauge size in accordance with appli cable codes Tighten the wire into lugs to the following torque...

Страница 7: ...ir operation Do not attempt manual operation of the transfer switch until after all power voltage supplies to the switch have been turned off Failure to turn off power voltage supplies may result in d...

Страница 8: ...equires adjustment If no load frequen cy is correct but voltage is not the voltage regu lator may require adjustment 3 4 GENERATOR TESTS UNDER LOAD 1 Set the generator s main circuit breaker to its OF...

Страница 9: ...7 Generac Power Systems Inc Section 4 Notes Generac 100 Amp Transfer Switch...

Страница 10: ...LOSING ALL CONTACTS SHOWN WITH TRANSFER SWITCH IN UTILITY TR 194 NOTE 194 A 23 23 B VR1 C1 A XA1 B B XB1 E1 6 9 205 126 TR 1 7 N2A E2 LEGEND F2 F4 N2 T2A VR2 T1A F3 T1 T2 N2A E2 N1 N1 N2 F1 F2 T2 T1 N...

Страница 11: ...28 77052 2 LUG 0 25 TAB 10 SCREW 29 81238 1 HARNESS WIRE 30 63378 2 CABLE TIE HOLDER 31 28739 2 TIE WRAP 4 32 75353 1 DECAL UL COMPONENT RECOGNITION 33 A9517 1 DECAL MANUAL OPERATION 34 A2595 1 DECAL...

Страница 12: ...replacement part s will void the warranty in its entirety 5 Damage related to rodent infestation 6 Failures due but not limited to normal wear and tear accident misuse abuse negligence or improper in...

Отзывы: