3.1 BEFORE 

INITIAL 

START-UP

Before starting, complete the following:
1. Set the generator's Auto/Off/Manual switch to the

OFF position.

2. Turn OFF the utility power supply to the transfer

switch using the means provided (such as the

utility main line circuit breaker).

3. Check the engine crankcase oil level and, if neces-

sary, fill to the dipstick FULL mark with the rec-

ommended oil. Do not fill above the FULL mark.

4. Check the fuel supply. Gaseous fuel lines must

have been properly purged and leak tested in

accordance with applicable fuel-gas codes. All

fuel shutoff valves in the fuel supply lines must

be open.

Never operate the engine with the oil level
below the “Add” mark on the dipstick. Doing
this could damage the engine.

3.2 CHECK 

TRANSFER 

SWITCH OPERATION

Refer to Section 2.4 (Page 19) for manual operation

procedures.

Do not attempt manual transfer switch 
operation until all power voltage supplies to
the transfer switch have been positively turned
off. Failure to turn off all power voltage 
supplies will result in extremely hazardous 
and possibly fatal electrical shock.

3.3 ELECTRICAL 

CHECKS

Complete electrical checks as follows:
1. Turn on the utility power supply to the transfer

switch using the means provided (such as a utili-

ty main line circuit breaker).

The transfer switch is now electrically “hot.”
Contact with “hot” parts will result in extremely
hazardous and possibly fatal electrical shock.
Proceed with caution.

2. Use an accurate AC voltmeter to check utility

power source voltage across terminals N1 and

N2. Nominal line-to-line voltage should be 240

volts AC.

3. Check utility power source voltage across termi-

nals N1 and the transfer switch neutral lug; then

across terminal N2 and neutral. Nominal line-to-

neutral voltage should be 120 volts AC.

4. When certain that utility supply voltage is com-

patible with transfer switch and load circuit rat-

ings, turn OFF the utility power supply to the

transfer switch.

5. Set the generator's main circuit breaker to its

OFF (or open) position. Initial tests will be con-

ducted at no-load condition.

6. On the generator panel, set the Auto/Off/Manual

switch to MANUAL. The engine should crank

and start.

7. Let the engine warm up for about five minutes to

allow internal temperatures to stabilize. Then, set

the generator’s main circuit breaker to its ON (or

closed) position.

Proceed with caution! Generator power voltage
is now supplied to the transfer switch. Contact
with live transfer switch parts will result in
dangerous and possibly fatal electrical shock.

8. Connect an accurate AC voltmeter and an AC fre-

quency meter across transfer switch terminal

lugs E1 and E2. Voltage should be 242-252 volts;

frequency should read about 61-63 Hertz.

9. Connect the AC voltmeter test leads across termi-

nal lug E1 and neutral; then across E2 and neu-

tral. In both cases, voltage reading should be 121-

126 volts AC.

10. Set the generator’s main circuit breaker to its

OFF (or open) position. Let the engine run at no-

load for a few minutes to stabilize internal engine

generator temperatures.

11. Set the generator's Auto/Off/Manual switch to

OFF. The engine should shut down.

NOTE:

It is important that you DO NOT proceed until you
are certain that generator AC voltage and frequen-
cy are correct and within the stated limits.
Generally, if both AC frequency and voltage are
high or low, the engine governor requires adjust-
ment. If frequency is correct, but voltage is high or
low, the generator’s voltage regulator requires
adjustment.

3.4  GENERATOR TESTS UNDER LOAD

To test the generator set with electrical loads applied,

proceed as follows:
1. Set generator’s main circuit breaker to its OFF

(or open) position.

2. Set the generator's Auto/Off/Manual switch

to OFF.

3. Turn OFF the utility power supply to the transfer

switch, using the means provided (such as a util-

ity main line circuit breaker).

Section 3 — Post-installation Start-up Adjustments

Guardian Air-cooled Generators

Содержание 04077-01, 04109-1, 04079-1, 00

Страница 1: ...ustment Manual Air cooled Prepackaged Standby Generators Models Nonsound Attenuated Non SA 04077 1 6 kW 04109 1 8 kW 04079 1 10 kW Sound Attenuated SA 00789 1 8 kW 00844 1 8 kW ONLY QUALIFIED ELECTRIC...

Страница 2: ...s symbol points out important safety informa tion that if not followed could endanger personal safety and or property of you and others This symbol points out potential explosion hazard This symbol po...

Страница 3: ...5 1 16 Grounding the Generator 15 1 17 The Battery 16 1 17 1 Battery Installation 17 1 18 The Fuse 17 1 19 Post Installation Inspection 17 Section 2 Operation 18 2 1 Using the Auto Off Manual Switch 1...

Страница 4: ...sufficient concentrations can cause unconsciousness or even death This exhaust sys tem must be installed properly in strict compli ance with applicable codes and standards Following installation you m...

Страница 5: ...ediate medical help Never wear jewelry when working on this equip ment Jewelry can conduct electricity resulting in electric shock or may get caught in moving com ponents causing injury FIRE HAZARDS F...

Страница 6: ...tion 85 John Street New York N Y 10038 7 AGRICULTURAL WIRING HANDBOOK available from the Food and Energy Council 909 University Avenue Columbia MO 65201 8 ASAE EP 3634 INSTALLATION AND MAINTE NANCE OF...

Страница 7: ...s it may shift on lifting pipes during transportation which may result in injury The generator was not designed to be lifted by its roof Use the lifting holes or brackets provided near the base of the...

Страница 8: ...st spark can ignite such fuels and cause an explosion No leakage of fuel is permitted Natural gas which is lighter than air tends to collect in high areas LP gas is heavier than air and tends to settl...

Страница 9: ...rete pad Remove the packing material from the unit and unbolt the two 4 inch by 4 inch wooden blocks from the underside of the mounting base Plug the holes with the plugs provided Prepare the installa...

Страница 10: ...8 Generac Power Systems Inc Figure 1 4 Generator and Transfer Switch Mounting Dimensions 6 kW 8 kW and 10 kW Non SA Section 1 Installation Guardian Air cooled Generators...

Страница 11: ...Generac Power Systems Inc 9 Figure 1 4 Continued Section 1 Installation Guardian Air cooled Generators...

Страница 12: ...10 Generac Power Systems Inc Figure 1 5 Generator Mounting Dimensions Sound Attenuated Section 1 Installation Guardian Air cooled Generators...

Страница 13: ...ty is supply ing 120 240 volt single phase electrical service 1 9 TOTAL CIRCUIT ISOLATION METHOD If essential electrical loads cannot be grouped togeth er and wired into an emergency distribution pane...

Страница 14: ...e a length of flexible conduit between the generator and any rigid conduit NOTE See also Emergency Circuit Isolation Method Section 1 8 and Total Circuit Isolation Method Section 1 9 on Page 11 1 11 1...

Страница 15: ...Section 1 Installation Guardian Air cooled Generators Figure 1 10 Interconnection Diagram for Single Phase Power System Sound Attenuated Figure 1 9 Interconnection Diagram for Single Phase Power Syste...

Страница 16: ...l module circuit board in the control panel Refer to the Operation section of this manual 1 13 CONTROL CIRCUIT INTERCONNECTIONS For 6 kw 8 kW and 10 kW units not including sound attenuated these inter...

Страница 17: ...dip switches see Figure 1 12 which may be set up differently during installation 1 Dip switch 1 When in the ON position the board requires 20 Vac from the step down transformer to the control board t...

Страница 18: ...of the battery and Disconnect charging source prior to connecting or dis connecting battery terminals Do not open or mutilate the battery Released electrolyte has been known to be harmful to the skin...

Страница 19: ...black battery cable from frame ground to the battery post indicated by a nega tive NEG or Figure 1 14 Battery Cable Connections NOTE With the battery installed and utility power source voltage availab...

Страница 20: ...el or during the normal exercise cycle To prevent possible injury that might be caused by such sudden starts always set the switch to OFF and remove the fuse before working on or around the generator...

Страница 21: ...ts timing E Retransfer Time Delay This timer runs for about 15 SA six seconds At end of a 15 second SA six second delay circuit board action de energizes transfer relay in the transfer switch Retransf...

Страница 22: ...uipped with the following systems that protect it against potentially damaging conditions 1 Low Oil Pressure Sensor 2 High Temperature Sensor 3 Overcrank 4 Overspeed On sound attenuated models there a...

Страница 23: ...should be wired to the unit by a qualified electrician or Generac Guardian Authorized Dealer 2 Remote Common Alarm This allows for an alarm light horn etc to activate when any fault has occurred Lines...

Страница 24: ...r switch and load circuit rat ings turn OFF the utility power supply to the transfer switch 5 Set the generator s main circuit breaker to its OFF or open position Initial tests will be con ducted at n...

Страница 25: ...ing the means provided such as a util ity main line circuit breaker 4 Set the Auto Off Manual switch to AUTO The sys tem is now ready for automatic operation 5 Turn OFF the utility power supply to the...

Страница 26: ...t to obtain 62 Hertz at no load 7 When frequency is correct at no load check the AC voltage reading If voltage is incorrect the volt age regulator may require adjustment Figure 3 1 6 kW Engine Governo...

Страница 27: ...emove the roof to adjust the voltage regulator on nonsound attenuated units Figure 3 4 Voltage Adjustment Potentiometer NOTE The voltage regulator is housed in the generator s control panel The regula...

Страница 28: ...s disconnected and then reconnected The exerciser WILL NOT work if dip switch 2 Remote Not Auto is ON 3 10 2 SOUND ATTENUATED UNITS The generator will start and exercise once every seven days During t...

Страница 29: ...4 Replace control board The Auto Off Manual switch 1 Defective Auto Off Manual 1 Replace switch is set to OFF but the engine switch continues to run 2 Auto Off Manual switch 2 Check wiring and connect...

Страница 30: ...LECTRICAL CONNECTIONS Complies with local code requirements and all National Electrical Codes Utility is connected and present Transfer switch is connected All wires running outside of the generator a...

Страница 31: ...Generac Power Systems Inc 29 Section 5 Notes Guardian Air cooled Generators...

Страница 32: ...Part No C4219 GENERAC POWER SYSTEMS INC P O BOX 8 WAUKESHA WI 53187 Revision 12 13 99 Printed in U S A...

Отзывы: