Chapter 2
TRANSPORTING THE DRILLING RIG
8
2.
Hook the tool (upper element) to the rope of the secondary winch.
3.
Go to a safe area.
4.
Lift the tool until the two parts of the joint are aligned.
5.
Lean the ladder against the mast.
6.
When a second operator at the base guarantees the stability of the
ladder by holding it with both hands, climb up to the height of the rotary
joint and secure the safety belts to the eyebolt on the mast.
7.
Push the tool so that the male and female parts of the joint are aligned
both axially and with the surfaces of the hexagon.
8.
Lower the rotary-shaft to compose the joint.
9.
Insert the pin and secure the safety bolt.
10.
Climb down the ladder and remove it.
Proceed as follows to assemble the central part of the auger
fig.2.1.1.1
:
Position the rotary at the up limit switch.
Hook the tool (lower element) to the rope of the secondary winch.
Lift the tool until the two parts of the joint are aligned.
Lean the ladder against the mast.
When a second operator at the base guarantees the stability of the
ladder by holding it with both hands, climb up to the height of the joint
and secure the safety belts to the eyebolt on the mast.
Push the tool so that the male and female parts of the joint are aligned
both axially and with the surfaces of the hexagon.
Lower the rotary to compose the joint.
Insert the pin and secure the safety bolt.
Climb down the ladder and remove it.