ITEM
DESCRIPTION
1
Cryogen vent (200mm [8"] O.D.)
2
Emergency exhaust vent - refer to magnet room vent requirements (position to be defined)
3
Pressure equalization vent - refer to magnet room vent requirements (position in ceiling to be
defined)
4
(2) 13mm [1/2"] I.D. High pressure hoses and (4) 25mm [1"] compression clamps. 150 Micron
filter, Shut off valves and By-pass valve as required.
MECHANICAL/PLUMBING NOTES
All piping, fittings, supports, hoses, clamps, ventlation systems, etc. are to be supplied and installed
by the customer or his contractors.
For complete design and requirements, specifications and guidelines refer to the pre-installation
manual: system cooling, cryogen venting, waveguides and exhaust venting.
An emergency water cooling back-up supply is recommended for continuous cryogen compressor
operation. if using an open loop back-up design, ensure a drain is provided. please refer to the
pre-install manual for optional back-up coolant supply requirements
Date
Rev
/24
EN-MRI-TYP-SIGNA_EXPLORER-WEB.DWG
A
03/Aug/2018
SIGNA EXPLORER /SIGNA CREATOR
Typical
M1 - Mechanical Layout
14
MAGNET ROOM
EQUIPMENT ROOM
CONTROL ROOM
1
13.76
16.2
2
3
4
9'-4"
11'-6"