1900/27 Vibration Monitor Operation and Maintenance Manual
20
To install the cable to the terminal strip follow these steps:
1. If an outer jacket is on the power cable then strip off about 25 mm (1
in) of outer insulation from the cable.
2. Strip 6 mm (0.25 in) of insulation from each of the conductors that
will be connected to the power terminals.
3. Crimp a ring or spade lug to each of the conductors using the crimp
tool.
4. Open the hinged protective cover over the power and relay terminal
strip.
5. Place each lug under the proper screw on the power terminal strip
(see Figure 2-13) and use the screwdriver to tighten the screw.
Figure 2-13: Power Connections 6. Close the hinged protective cover over the terminal
strip.