SB-7-622 Page 10
SECTION 2
INSTALLATION
LOCATION
Install the blower in a well lit, clean dry place with
plenty of room for inspection and maintenance.
FOUNDATIONS
For permanent installation we recommend concrete
foundations be provided, and the equipment should
be grouted to the concrete. It is necessary that a
suitable base be used, such as a steel combination
base under blower and motor, or a separate sole
plate under each. Before grouting, equipment must
be leveled, free of all stains, and anchored so no
movement will occur during setting of grout. After
grout has completely hardened, a recheck is
necessary to compensate for shrinkage, etc. If
required, add shims under blower feet after final
tightening of foundation anchor bolts to remove
strain from the blower housing.
Where jack screws or wedges are used during
grouting, they must be backed off and wedges
removed before final tightening of anchor bolts.
Refer to grouting instructions.
Where a concrete foundation is not feasible, care
must be taken to insure that equipment is firmly
anchored to adequate structural members,
restricting movement and vibration.
MOUNTING CONFIGURATIONS
The blower flex-mount design enables horizontal
and vertical mounting configurations with top or
bottom hand, right or left hand shaft positioning.
The units are center timed allowing rotation in either
direction (refer to Figure 2-1). If converting a blower
from vertical to horizontal, or horizontal to vertical
mounting configuration, additional mounting feet will
be required.
REPOSITIONING THE MOUNTING FEET.
1. Position the mounting feet to the desired
location and snug the capscrew.
2. Place the blower on its feet on a flat surface.
3. Loosen mounting feet capscrews and level unit
up. The bench or blower base flatness should be
within .002 of an inch.
NOTICE
If the unit is not flat within .002 of an inch, it
will be necessary to shim the blower feet at
installation.
FIGURE 2- 1
– BLOWER MOUNTING CONFIGURATIONS
Содержание GAF P Series
Страница 19: ...SB 7 622 Page 18 SECTION 5 MAINTENANCE FIGURE 5 1 PULLER PLATE SK2154...
Страница 20: ...SB 7 622 Page 19 FIGURE 5 2 GEAR DRIVEN SK2150...
Страница 21: ...SB 7 622 Page 20 FIGURE 5 3 MECHANICAL SEAL INSTALLATION TOOL SK2152...
Страница 22: ...SB 7 622 Page 21 FIGURE 5 1 BEARING PRESS TOOL MECHANCIAL SEAL UNITS SK2156 FIGURE 5 4...
Страница 33: ...SB 7 622 Page 32 SECTION 8 PARTS LIST 300GAF810 B Ref Drawing...
Страница 35: ...SB 7 622 Page 34 300GAG810 A Ref Drawing...
Страница 37: ...SB 7 622 Page 36 300GAH810 A Ref Drawing...
Страница 39: ...SB 7 622 Page 38...