36
U41662-J-Z156-1-76
Installing/Removing the Server into the Rack
Hardware Installation
–
Please ensure the functionality of the security mechanisms (e. g. stopper or
retention systems) on the server.
–
The form of the rack support uprights must ensure the frontal screwing on of
the rails.
–
Frontally bolted telescopic rails or sliding rails.
The rails are provided with a linear alignment possibility to ensure an
adjustment to different rack depths.
–
No support of the cable management delivered with the mounting kit.
–
Climatic conditions.
For the ventilation of the installed server, an unhindered air intake in the rack
front and an air discharge in the rear cover of the rack are necessary.
In principle the ventilation concept plans that the necessary cooling is
reached by the horizontal self-ventilation of the installed devices (air flow
from the front to the rear).
–
Power supply.
For the installation in 3rd-Party Racks it is to be made certain that appro-
priate socket strips are present.