BX900S2
Operating Manual
51
Hardware installation
5.2.1
Installation in PRIMECENTER/DataCenter rack
For installation in a PRIMECENTER/DataCenter rack, the following parts are
required:
– One 10-HU support bracket (option for asymmetrical rack like
PRIMECENTER/DataCenter rack)
– Two carrier rails (right and left rail)
– Two holding-down clamps
– Six M5 screws including plugwashers
– Ten M5 centering screws
– Four cage nuts
I
– The descriptions and figures in this section refer to the current
support system. For other support systems you will find the
appropriate description in the packaging of the rack mounting kit.
– General information regarding server installation in the rack is
included in the manual for the appropriate rack.
Positioning the system unit in the rack
The BX900 S2 system unit occupies 10 Height Units (HU) in the rack. The
figure 4
and
figure 5
show the position of the screws and cage nuts for securing
the carrier rails, holding-down clamps and the system unit.
I
The figures below refer to the symmetrical rack. There is no support
bracket. The holding-down clamp and the carrier rail are installed directly
on the support upright.