(7) When using the heating pipe, perform heating work or thermal insulation treatment as required
(Fig.5-6). Otherwise, condensation may be caused at the outlet of the extractor.
If terminal processing is performed inside the gas extractor and only heated parts are pulled out
-
side, heating work will not be necessary.
Piping heating work
Teflon tube in
the heating pipe
Extractor
Heating pipe
Fig. 5-6
5.4 Wiring
Open the gas extractor box, and supply heater power of 100 V AC, 400 W to the internal terminal.
When the temperature of the installation location becomes high, heat-proof cables should be used
for wiring.
100 V AC
400 W
Wired
Wired
Fig. 5-7 Terminal
Heater
Terminal
2
3
4
1
Thermostat
Power supply
100 V AC, 400 W
Fig. 5-8 Connection diagram