163
EN
However, on the DC disconnector, the measurements should only be taken at the screws,
not the contacts.
1 Measuring device
2 Inverter
9 Measuring line
Examples of measuring the insulation resistance.
Overvoltage PC board (5)
Capacitor discharge time is at least 6 min.
Ground conduc-
tor resistance
-
Only perform the measurement if the insulation resistance test produced an accept-
able result.
-
Fit the cover back onto the inverter.
-
Correct functioning of the ground conductor is only guaranteed if the results of the
measurement between the cover and the wall bracket are acceptable.
-
The device being tested must be safely isolated from the AC grid (the grid lead [L, N]
must not be connected). If the AC grid cannot be disconnected from the wall bracket,
the relevant safety precautions must be taken.
-
Place the inverter back in the wall bracket.
Ground to AC / Ground to DC
Symo 10-20, Eco
Symo 10-20
Eco
(5)
(5)
WARNING!
An electric shock can be fatal. Capacitors can charge during the in-
sulation resistance measurement. After carrying out the insulation resistance test,
check that all tested potentials are de-energised before continuing with the safety
inspection. Alternatively, the capacitors can be discharged by short-circuiting the
tested potentials or via the discharge function on the insulation tester.
CAUTION!
Take safety precautions. Observe the safety rules - DC voltage pres-
ent!
WARNING!
Set the inverter DC disconnector to the 0 position and place the in-
verter in the wall bracket. Placing the inverter in the wall bracket causes a voltage
to be applied to the inverter.
Содержание 10.0-3 480
Страница 2: ...2 ...
Страница 5: ...Allgemeine Informationen ...
Страница 6: ......
Страница 13: ...Fehler Suchhilfe ...
Страница 14: ......
Страница 33: ...Komponenten austauschen ...
Страница 34: ......
Страница 40: ...40 Gewindebuchsen in der Grundscha le tauschen 1 2 3 4 5 1 2 3 4 5 ...
Страница 41: ...41 DE 6 6 ...
Страница 73: ...Sicherheitstechnische Überprüfung ...
Страница 74: ......
Страница 86: ...86 ...
Страница 89: ...General information ...
Страница 90: ......
Страница 97: ...Error location aid ...
Страница 98: ......
Страница 116: ...116 ...
Страница 117: ...Changing components ...
Страница 118: ......
Страница 124: ...124 Replacing thread ed bushings in the base shell 1 2 3 4 5 1 2 3 4 5 ...
Страница 125: ...125 EN 6 6 ...
Страница 156: ...156 ...
Страница 157: ...Safety Inspections ...
Страница 158: ......
Страница 170: ...170 ...
Страница 171: ...Appendix ...
Страница 176: ...176 Circuit diagrams Fronius Symo ...
Страница 177: ...177 Circuit diagrams Fronius 15 0 ...
Страница 178: ...178 ...
Страница 179: ...179 ...