6 | Commissioning
56
M2050222_en | Installation instructions Lambdamat LM 1500 KOM
6 Commissioning
6.1 Before commissioning / configuring the boiler
The boiler must be configured to the heating system during initial start-up!
NOTICE
Optimum efficiency and efficient, low-emission operation can only be guaranteed if the
system is set up by trained professionals and the standard factory settings are observed.
Take the following precautions:
r
Initial startup should be carried out with an authorised installer or with Froling
customer services
NOTICE
Foreign bodies in the heating system impair its operational safety and can result in
damage to property.
As a result:
r
The whole system should be rinsed out before initial start-up in accordance with EN
14336.
r
Recommendation: Make sure the hose diameter of the flush nozzles in the flow and
return complies with ÖNORM H 5195 and is the same as the hose diameter in the
heating system, however not more than DN 50.
r
Turn on the main switch
r
Set the boiler controller to the system type.
r
Load the boiler default values.
NOTICE! For the keypad layout and instructions for modifying the parameters, see
the instruction manual for the boiler controller.
r
Check the system pressure of the heating system.
r
Check that the heating system is fully ventilated
r
Check all quick vent valves of the entire heating system for leaks
r
Check that all water connections are tightly sealed
Ä
Pay particular attention to those connections from which plugs were removed
during assembly.
r
Check that all necessary safety devices are in place
r
Check that there is sufficient ventilation in the boiler room.
r
Check the seal of the boiler.
Ä
All doors and inspection openings must be tightly sealed.
r
Check all blanking plugs (e.g. drainage) for tightness
r
Check that the drives and servo motors are working and turning in the right direction
NOTICE! Check the digital and analogue inputs and outputs - See the instruction
manual for the boiler controller.