Pressure testing
Use
Dry Nitrogen
1.
Remove the valve caps on
the liquid valve and gas valve
and the nut of refrigerant port
2.
Connect the charging hose
of manifold to the refrigerant
port, and the other to the
nitrogen tank regulator.
3. (System should hold 550
Psig for one hour.)
Begin with-
a. 150 psig for 5 min.
b. 300 psig for 15 min.
c. 550 psig for 1 hour.
4. Test all connections with
bubble solution.
5. If no leaks are found proceed to vacuum steps below.