LAZERWELD II PLATE HEAT EXCHANGER

MAINTENANCE

5.   If the cassettes are correctly assembled, the edges 

form a honeycomb pattern, see picture below.

6.   Press the plate assembly together. Tightening is done 

in two steps, see substeps below. Be careful to ensure 
that the frame plate and the pressure plate are always 
in parallel. 

a.  Tighten the two diagonal pairs of bolts alternately 

until the plate package measures 1.10A. 

 
Be careful to ensure that the frame plate and pres-
sure plate are always in parallel. Skewing of the 
pressure plate during opening must not exceed 10 
mm (2 turns per bolt) across the width and 25 mm (5 
turns per bolt) vertically.

b.  After that, bolts are tightened alternately and diago-

nally. Check the dimension A during tightening at the 
positions of the bolts that are being used.

NOTICE

For the final tightening, alternate between bolts to 

reach dimension A.

Max tightening torque

When a pneumatic tightening device is used see Table 3 
for maximum torque. Measure dimension A during tight-
ening.

Table 3: Torque measurement

Bolt size

Bolt with 

bearing box

Bolt with wash-

ers

N·m

kpm

N·m

kpm

M24

450

45

M30

585

58

900

90

M39

1300

130

2000

200

M48

2100

210

3300

330

For manual tightening, the tightening torque has to be 
estimated.

If dimension A cannot be reached:

•  Check the number of cassettes and the dimension A.
•   Check that all the nuts and bearing boxes are running 

freely. If not, clean and lubricate, or replace.

•   Leave the LZWII between 24 to 48 hours, the longer 

the better, for gaskets to relax.

1.10A

1.10A

Содержание LZWII-12M

Страница 1: ...lt in personal injury or death damage to the unit or improper operation LaZerWeld II Plate Heat Exchangers LZWII 2M LZWII 4B LZWII 4E LZWII 6B LZWII 8K LZWII 8B and LZWII 12M Check www FrickCold com f...

Страница 2: ...rranty conditions 3 Advice 3 Environmental compliance 3 Unpacking 3 Maintenance 3 Scrapping 3 Main components 3 Nameplate 5 Function 5 Identification of plate side 6 Installation Before installing 7 R...

Страница 3: ...the date when the heat exchanger was put into operation to the local FRICK Representative ADVICE Consult your local FRICK representative for information on the following New plate pack dimensions if...

Страница 4: ...ns Port holes through the frame plate allow the media to enter into or exit from the heat exchanger Different types of connections can be used to connect the piping system to the apparatus Threaded st...

Страница 5: ...fied on the assembly drawing are to be exceeded consult the supplier Figure 3 Nameplate Material No FRICK Sales Order No Tag No Optional FOR PARTS SERVICE AND AFTER MARKET ASSISTANCE CALL 1 717 762 21...

Страница 6: ...by the stamp with the letter A or the model name in some cases both at the top of the plate See Figure 4 The separate ring gaskets always point to the right when the cassette is oriented as A End cass...

Страница 7: ...awing Foundation Install on a flat foundation giving enough support to the frame Elbow To allow easier disconnection of the LZWII connect an el bow to the pressure plate using a flange directed upward...

Страница 8: ...B Figure 10 Lifting divice for LZWII 12M RAISING This instruction is valid when raising the LZWII after delivery The strap is approved for the weight of the heat exchanger to be used CAUTION The strap...

Страница 9: ...n CONNECTING TO THE SYSTEM Remove sealing blind covers from the port holes before connecting the piping system When connecting the piping system make sure the pipes do not subject the LZWII to stress...

Страница 10: ...190 210 IOM FEB 20 Page 10 LAZERWELD II PLATE HEAT EXCHANGER INSTALLATION This page is intentionally left blank...

Страница 11: ...levels might be lower than any elasto meric materials can seal against In applications where the field side is used for a two phase refrigerant for example cascade CO2 NH3 ap plications it is very im...

Страница 12: ...e LZWII drawing and identification plate SHUT DOWN If several pumps are included in the system make sure you know which one to stop first 1 Slowly close the valve controlling the flow rate of the pump...

Страница 13: ...ARNING Use proper protective equipment such as safety boots safety gloves and eye protection when using the cleaning agents WARNING Corrosive cleaning liquids can cause serious injuries to skin and ey...

Страница 14: ...iding surfaces of the carrying bar and clean and grease it 4 Mark the cassette assembly on the outside with a diagonal line 5 Measure and note the dimension A NOTICE Brush the threads of the tightenin...

Страница 15: ...es do not need to be removed if cleaning is done using only water or without cleaning agent WARNING The plate pack may still contain a small residual amount of liquid after draining Depending on the t...

Страница 16: ...ts and ring gaskets affixed to the cassettes using glue free Clip on tabs NOTICE Before removing the old gaskets check how they are placed and attached Especially the end cassette gasket configuration...

Страница 17: ...t place ment of the respective cassette type can be advised by your FRICK representative 6 Close the heat exchanger see Closing Glued gaskets Use glue recommended by FRICK Separate gluing instruc tion...

Страница 18: ...ter that bolts are tightened alternately and diago nally Check the dimension A during tightening at the positions of the bolts that are being used NOTICE For the final tightening alternate between bol...

Страница 19: ...representatives reserve the right to in spect the storage space and or equipment whenever necessary until the date of expiry of the warranty period stipulated in the contract Notification has to be gi...

Страница 20: ...vice for an extented period of time for example longer than one year the risk of leakage when starting up increases To avoid this problem let the gasket rubber rest and regain most of its elasticity 1...

Страница 21: ...190 210 IOM FEB 20 Page 21 LAZERWELD II PLATE HEAT EXCHANGER MAINTENANCE Notes...

Страница 22: ...ynesboro PA 17268 1206 USA Phone 717 762 2121 FAX 717 762 8624 www johnsoncontrols com FRICK Form 190 210 IOM 2020 02 Supersedes NOTHING Subject to change without notice Published in USA 02 20 PDF 202...

Отзывы: