EMG 1500 Operating Manual 

Installation 

 

 

3.2.1 Power supply 

The  instrument  requires  a  230  V  AC,  50/60  Hz  power  supply.  Der 
This  is  connected  at  the  “230V

∼∼∼∼

”  terminals  as  shown  in  the  wiring 

diagram Figure 1, Seite 6. 

   Important: 

The  instrument  power  supply  must  be  provided  with  2  A 
external overcurrent protection. 
 
 

3.2.2 Connection to the Ethernet 

The EMG 1500-PN is connected to a hub or switch via the shielded 
RJ45  jack  (10BaseT)  at  the  front  of  the  instrument.  The  pin 
assignment corresponds to that of an MDI port, so that a 1:1 cable 
must be used. 
 

3.2.3 Connection to the FRAKO Starkstrombus

®

 

The  terminals  “Bus  A,  “Bus  B”  and  “Bus 

⊥⊥

”  are  provided  for 

connecting to the FRAKO Starkstrombus

® 

as shown in Figure 1, on 

page 6.  
The  two  poles  of  the  two-wire  bus  are  connected  to  terminals  “A” 
and  “B”,  attention  being  paid  to  the  correct  polarity,  while  the 
shielding  is  connected  to  the  “

⊥⊥

 

terminal.  The  “A”  terminal  is  thus 

connected  with  all  the  other  A  terminals  of  the  bus,  and  the  same 
applies to the B and “

⊥⊥

” terminals. (No crossover in the cables!) 

   Important: 

The bus shielding (

⊥⊥

) must be earthed only at one point in the 

bus  system.  If  this  has  not  already  been  arranged  at  another 
point, it should be done at the EMG 1500-PN. 
 
The bus must have a single-segment topology, all instruments being 
patched in to this segment or connected to it by a drop line up to 2 
m in length. Star topologies can be constructed by using a repeater 
(component EMB 1101). 

The  total  length  of  the  bus  should  not  exceed  1200 m. A repeater 
(component  EMB  1101)  must  be  installed  in  the  line  if  greater 
distances are needed. 

Содержание EMG 1500-PN

Страница 1: ...Gateway EMG 1500 PN EMG 1500 PN Energy Management System Run Made in Germany Gateway Serial Ethernet Connect Bus error Bus Operating manual EMG 1500 PN...

Страница 2: ...ollow the operating manual The installation and commissioning may only be carried out by appropriately qualified personnel with due regard for all rules and regulations that are in force The instrumen...

Страница 3: ...Connection to the FRAKO Starkstrombus 7 3 2 4 RS 232 connection 8 4 Commissioning 9 4 1 Preparations before commissioning 9 4 2 Instrument self test 9 4 3 Assigning an IP address 9 4 3 1 Assigning the...

Страница 4: ...s used to carry out all network settings i e IP address subnet mask and gateway see Section4 3 page 9 The supply voltage must then be removed from the instrument Installation The instrument is mounted...

Страница 5: ...SW is used to configure the EMG 1500 PN The EMIS 1500 central unit uses the EMG 1500 PN to access the individual instruments in the Energy Management System and collect their data The Setup programs...

Страница 6: ...ards or control cabinets When the instrument is in operation it must not be possible to touch the instrument terminals 3 2 Electrical connections The instrument is connected according to the wiring di...

Страница 7: ...shown in Figure 1 on page 6 The two poles of the two wire bus are connected to terminals A and B attention being paid to the correct polarity while the shielding is connected to the terminal The A ter...

Страница 8: ...ogether and shielded Types Manufacturer cable type order number cable Twinax 105 Lapp Unitronic Bus CAN 1x2x0 34 2170263 6 8 mm Helukabel CAN BUS 1x2x0 34 801572 6 5 mm Leoni L 02YSCY 1x2x0 34 2 0 120...

Страница 9: ...e per second 4 3 Assigning an IP address The EMG 1500 PN requires a unique IP address before it can be accessed via the Ethernet The address is assigned using the software EMG SW supplied as part of t...

Страница 10: ...there is at least one data collector of the type EMIS 1500 In addition a connection with this data collector must be in existence An additional bus coupler can be added by clicking the right mouse bu...

Страница 11: ...Max Number of masters should not be changed and should remain set at 8 Important Each bus address may only be assigned once within a bus system For larger systems it is recommended to draw up a table...

Страница 12: ...established with the EMG 1500 PN The Bus error LED indicates that there are bus related problems in the FRAKO Starkstrombus Each time this LED comes on it indicates that there has been an error in th...

Страница 13: ...has not been adopted Switch the device off and then on again After the Ethernet cable has been plugged in the device cannot be accessed During device start up no Ethernet connection could be detected...

Страница 14: ...lectrical connection as per EIA RS 485 Transmission rate 76 8 kbit sec Protocol FRAKO Starkstrombus Ethernet interface Plug RJ45 Transmission 10BaseT half duplex Mechanical design Enclosure material P...

Страница 15: ...ta 15 EMG 1500 PN Energy Management System Run Made in Germany 140 0 mm 11 4 mm 5 0 mm 59 2 mm Gateway Serial Ethernet Connect Bus error Bus 44 8 mm 35 0 mm 90 0 mm 4 5 mm Figure 3 Enclosure dimension...

Страница 16: ...e filters Dynamic compensation of harmonics Reactive power control relays Maximum demand control systems Mains monitoring instruments Cost allocation Energy management systems Sales programme EMG 1500...

Отзывы: