4 Boiler test 

 
Boiler test (or new boiler 
first operation) must be 
performed exclusively by 
qualified personnel. 
 
4.1 Preliminary checks 
Before carrying out any test 
(or starting the boiler for the 
first time), perform the 
following checks: 
- the installation must comply 
with applicable laws; 
- the flue gas outlet duct and 
the end section are installed in 
compliance with instructions: 
when the boiler  is switched 
on there must be no
 leakage 
of combustion products
 
from any of the seals; 
- power supply is 230 V - 50 
Hz; 
- system is loaded (water 
pressure gauge reads 0.8/1 
bar); 
- cut-off valves on the system 
pipes are open; 
- gas mains supply according 
to boiler factory-set gas: in 
case of discrepancy, convert 
the boiler to the gas type 
available, see “SWITCHING 
TO DIFFERENT GASES“ 
section in this manual; 
- gas mains tap is open; 
- no gas leaks are detected; 
- boiler is electrically powered; 
- boiler safety valve is not 
locked; 
- no water leaks are detected. 
 
Should boiler not be 
installed complying with 
applicable standards and 
laws, do not start it and 
notify immediately the 
central heating system 
supervisor. 
 
 
 
 
4.2 Turning the boiler on or 
off 

Follow the “Users’ 
Instructions”  
for boiler on 
and off procedure. 

 

5 Maintenance 
 

B

oiler must be yearly serviced 

to ensure efficient and trouble- 
free operation. 

 

 
Maintenance (or repair) 
operations must be 
performed exclusively by 
qualified personnel. 
 
Disconnect the boiler from  
power mains before 
beginning any maintenance 
procedure either involving 
replacement of components 
and/or internal cleaning. 
 
Maintenance list 
Routine maintenance must 
include the following checks: 
 
- boiler integrity ; 
- leakage of the boiler’s gas 
circuit and gas mains network; 
- boiler gas supply pressure; 
- minimum and maximum gas 
pressures to the boiler 
nozzles; 
- boiler ignition; 
- boiler combustion 
parameters through flue gas 
analysis (to be performed on a  
two-year basis if boiler is 

 

individually installed. Annually 
to cascade-installed boilers); 
- general condition and leak 
check of flue system including 
anti-wind gust device (BTN - 
balanced flue - model); 
- absence of flue gas reflux 
into the premises and correct 
exhaust of flue gas (BTN – 
balanced flue - model); 
- condition of safety 
thermostat installed on the 
anti-wind gust device (BTN – 
balanced flue - model); 
- air pressure switch (BTFS – 
forced draught - model); 

- general condition of e boiler 
safety devices; 
- water leaks and scaling of 
boiler connections; 
- efficiency of the CH safety 
valve; 
- efficiency of the DHW safety 
valve; 
- expansion vessel working 
pressure; 
- water pressure switch 
efficiency; 
- magnesium anode efficiency. 
 
And the following cleaning 
operations: 
 
- general internal cleaning; 
- gas nozzles; 
- air intake and flue gas outlet 
circuit (BTFS – forced draught 
- model); 
- anti-wind gust device (BTN – 
balanced flue - model); 
- room ventilation grille if 
available (BTN – balanced flue 
- model); 
- heat exchanger (flue gas 
side). 
In case of new boiler first 
operation,  also check: 
- boiler room characteristics 
according to boiler 
requirements; 
- room ventilation grilles, if 
available (BTN – balanced flue 
- model); 
- flue system dimensions, 
diameters and lengths of 
ducts; 
- correct installation of the 
boiler in compliance with the 
instructions in this manual. 
 
Should the boiler not be 
installed according to this 
manual operating require-
ments, if there is no 
immediate danger or hazard 
to people, animals and 
property, notify, both 
verbally and in writing, the 
system supervisor. 

Содержание NIAS BTN 28

Страница 1: ...NIAS INSTALLATION USE AND MAINTENANCE GB IST 03 C 167 01...

Страница 2: ...Thank you for choosing our boiler Please read these installation and maintenance instructions with care Please note that the boiler must only be installed repaired and serviced by qualified personnel...

Страница 3: ...the packaging as all the materials can be recycled The packaging must therefore be sent to specific waste management sites Keep the packaging out of the reach of children as it may represent a choking...

Страница 4: ...sitioning the boiler page 13 3 2 4 Installing the boiler page 14 3 2 5 Boiler room ventilation page 15 3 2 6 Flue system page 15 3 2 7 Flue system configuration page 17 3 2 8 Flue system with coaxial...

Страница 5: ...the water storage tank from freezing is active Power light B The light indicates that power is being supplied to the boiler Central Heating temperature regulator C The knob sets the heating system wat...

Страница 6: ...re or qualified maintenance personnel If the boiler shuts down frequently this indicates that there is a recurring malfunction In this case contact qualified personnel or an authorised Service Centre...

Страница 7: ...es or until the temperature of the water in the system reaches 15 C WARNING This function is not active if the boiler is disconnected from the power and gas supply and the gas tap is closed The heatin...

Страница 8: ...ruary 1973 amended by Directive 93 68 EEC dated 22 July 1993 NIAS boilers are equipped with safety features according to applicable laws The main technical features of NIAS boilers are below summarize...

Страница 9: ...e 11 Temperature probe 12 Expansion vessel heating system 13 Optional expansion vessel DHW system 14 Water storage tank anode 15 Water storage tank 16 Water storage tank thermostat 17 Overheating shut...

Страница 10: ...HW production by 45 C t 8 9 lts min DHW production by 35 C t 11 5 lts min DHW production by 40 C t 10 lts min DHW production by 30 C t 13 4 lts min 45 C DHW supply during the first 10 minutes storage...

Страница 11: ...4 BTN 28 W 110 Maximum absorbed power BTFS 24 BTFS 28 W 165 Net weight BTN 24 BTN 28 kg 72 5 Net weight BTFS 24 BTFS 28 kg 78 Natural gas consumption BTN 24 BTFS 24 m h min 1 32 max 2 80 Butane consum...

Страница 12: ...1 Flue gas mass g s 16 5 17 7 Flue air temperature C 108 8 CO2 5 9 Boiler efficiency 90 45 88 36 NIAS BTN 28 Heat dispersion from the boiler casing max input min input 30 red load Boiler installed ind...

Страница 13: ...e maintenance operations check wall sturdiness avoid fixing the boiler to thin partitions avoid installing the boiler above appliances which might affect boiler operation E G kitchen appliances emitti...

Страница 14: ...of the above To install the boiler fix the template to the wall by means of four 10 mm screws and dowels IMPORTANT ceiling and screws clearance must be 436 mm position connections of gas supply pipe...

Страница 15: ...conductivity it must be perfectly sealed to prevent cooling due to parasite air inlets it must be as vertical as possible and the end section must have a roof top which ensures efficient and constant...

Страница 16: ...tly check the flue outlet duct This duct may be obstructed or may be unsuitable for the discharge of flue gas into the atmosphere FONDITAL shall not be held responsible for damage resulting in incorre...

Страница 17: ...both end sections must be located within a 500 by 500 mm surface area C42 Boiler connected to collective chimneys including two ducts one for the air intake for combustion and the other for the discha...

Страница 18: ...the outlet point to prevent rain water from getting into the duct Type C32 Minimum length of vertical coaxial ducts is 0 5 meters Maximum allowable length of vertical coaxial ducts is 4 meters includ...

Страница 19: ...BTFS 24 model must be installed as shown in pic 11 diaphragms are supplied with boiler IMPORTANT Should flue system cross walls and or infrastructure or if it easily accessible it is mandatory to inst...

Страница 20: ...facing perimeter walls Maximum allowable load loss 80 Pa Sample No 2 pic 14 Air intake from perimeter wall and flue gas roof outlet Maximum allowable load loss 80 Pa Sample No 3 pic 15 Air intake fro...

Страница 21: ...elbows x 4 8 Pa splitting device 80 12 Pa horizontal 80 air intake terminal 3 Pa horizontal 80 outlet terminal 5 Pa Tot load loss 80 Pa 3 2 10 Measuring combustion efficiency Type A accessories Coaxi...

Страница 22: ...ing always use FONDITAL approved spare part FONDITAL shall not be held liable for damage on injury caused by failure to properly earth the power mains Gas lines DHW and CH pipes are not suitable for e...

Страница 23: ...rge any left air let the system cool down and then adjust water pressure gauge to 0 8 1 bar WARNING For best performance safe trouble free and long lasting operation of boiler and its components in or...

Страница 24: ...r dry any wet surfaces 3 4 Starting the boiler 3 4 1 Preliminary checks Before starting the boiler verify the following correct installation of flue gas outlet duct and the end section when the boiler...

Страница 25: ...brown blue yellow green Power supply 230 V 50 Hz Power supply 230 V 50 Hz CH DHW A1 A6 Utilities connectors AG Anti freeze DK Low water pressure safety switch E I Summer Winter switch IG Main switch...

Страница 26: ...en red teflon E ACC 1 white teflon E RIV pic 23 POWER OUTLETS Modulation board Modulation board black blue orange brown green white red brown blue brown blue black blue orange brown black black black...

Страница 27: ...ed with boiler must be installed For conversion and adjustment instruction see below Converting boiler from one type of gas to another remove the main burner remove nozzles 1 in pic 24 of main burner...

Страница 28: ...regulator pic 27 located on top of the modulation coil set the CH water temperature to maximum connect a U shaped pressure gauge following instructions shown in pic 28 set the heat power regulator P1...

Страница 29: ...nsequently the boiler heat output Burner gas pressure boiler heat output chart pic 30 Assuming the heating system requirement is 18 kW pic 30 chart indicates burner gas pressures to ensure proper boil...

Страница 30: ...owing checks boiler integrity leakage of the boiler s gas circuit and gas mains network boiler gas supply pressure minimum and maximum gas pressures to the boiler nozzles boiler ignition boiler combus...

Страница 31: ...31...

Страница 32: ...to 40 Tel 39 0365 878 31 Fax 39 0365 878 576 e mail info fondital it www fondital it The producer reserves the right to modify the data contained herein at any time without notice Uff Pubblicit Fondit...

Отзывы: