11
VISION • RIDE Technology
self-contained
Connect utilities to louvered docking assembly.
6
External connections
➊
➏
➌
➋
➐
➑
3/4" barb x 3/4" FPT
1" Stand pipe/Drain
2 ft. x 1" OD
silicone tubing
Minimum 8"
radius
3/4" MPT x 1" slip
➍
➎
➌
➋
➊
➏
3/4" barb x 3/4" FPT
1" Stand pipe/Drain
2 ft. x 1" OD
silicone tubing
Minimum 8"
radius
➍
3/4" MPT x 1" slip
➎
Air-cooled ice machines only
Water-cooled ice machines only
6.1
6.2
• Rough-in ice machine potable water
supply
➊
.
3/8" push-in connection will be made at
shut-off valve inside machine
• Remove access panel if necessary
➋
.
• Connect the silicone tubing to the ice
machine 3/4" drain barb
➌
.
• Assemble the 3/4" barb x 3/4" FPT to the
3/4" MPT x 1" slip. Connect the other end
of the silicone tubing to the 3/4" barb
➍
.
• Connect the 1" slip fitting to the 1" stand
pipe/drain
➎
.
Note: Minimum 8" radius on silicone
drain line. Drain line from the ice machine
must have at least 1/4" per foot pitch
(6,4mm/0,3m).
• Apply Petrol-gel to barbed drain fitting
➏
• Replace access panel.
• Rough-in ice machine potable water
supply
➊
.
3/8" push-in connection will be made at
shut-off valve inside machine
• Remove access panel if necessary
➋
.
• Connect the silicone tubing to the ice
machine 3/4" drain barb
➌
.
• Assemble the 3/4" barb x 3/4" FPT to the
3/4" MPT x 1" slip. Connect the other end
of the silicone tubing to the 3/4" barb
➍
.
• Connect the 1" slip fitting to the 1" stand
pipe/drain
➎
.
Note: Minimum 8" radius on silicone
drain line. Drain line from the ice machine
must have at least 1/4" per foot pitch
(6,4mm/0,3m).
• Connect cooling water supply
➏
and
return
➐
• Apply Petrol-gel to barbed drain fitting
➑
• Replace access panel.