5

Maintenance

WARNING

The V-notch ball closes with a
shearing, cutting motion, which could
result in personal injury. To avoid
injury, keep hands, tools, and other
objects away from the V-notch ball
while stroking the valve.

Avoid personal injury from sudden
release of process pressure. Before
performing any maintenance
operations:

D

Do not remove the actuator from

the valve while the valve is still
pressurized.

D

Disconnect any operating lines

providing air pressure, electric power,
or a control signal to the actuator. Be
sure the actuator cannot suddenly
open or close the valve.

D

Use bypass valves or completely

shut off the process to isolate the
valve from process pressure. Relieve
process pressure from both sides of
the valve. Drain the process media
from both sides of the valve.

D

Vent the power actuator loading

pressure and relieve any actuator
spring precompression.

D

Use lock-out procedures to be

sure that the above measures stay in
effect while you work on the
equipment.

D

Always wear protective gloves,

clothing, and eyewear when
performing any maintenance
operations to avoid personal injury.

D

The valve packing area may

contain process fluids that are
pressurized, 

even when the valve has

been removed from the pipeline

.

Process fluids may spray out under
pressure when removing the packing
hardware or packing rings.

D

Check with your process or safety

engineer for any additional measures
that must be taken to protect against
process media.

Packing Maintenance

1.  It is recommended that the valve be removed
from the line when replacing packing to allow correct
set up of the actuator after actuator removal.

2.  Remove the packing follower nuts and packing
follower (keys 18 and 16).

3.  Remove the packing parts (see figure 4 and 
keys 15 and 14) using a purposed designed packing
extraction tool to avoid damaging the packing box
bore and shaft surfaces.

4.  Install the new packing parts using the sequence
shown in figure 4. Fit the packing follower (key 16).
Fit nuts (key 18).

5.  Tighten the packing nuts to compress the packing
to seal for operating conditions. At the same time
push the ball and shroud on the drive end against
the valve body inside location face to center the ball.
This can be done by using a lever (wood) against
the inside ball lug face and the valve body liner inlet.

Disassembly

WARNING

Observe the steps in the WARNING at
the beginning of the Maintenance
section.

Reference figures 9 and 10.

CAUTION

Trim parts are made from brittle
material, handle with care to avoid
chipping or breakage.

1.  Remove the actuator cover (where applicable).
Take note of the orientation of the actuator with
respect to the valve body and the lever orientation
with respect to the valve drive shaft.

2.  Remove the actuator.

3.  Remove the flow ring retainer screws, clips and
flow ring retainer (keys 22, 23, and 5).

4.  Knock or press out the flow ring (key 4).

5.  Position the ball to allow access to the shaft pins.
Use a modified parallel pin punch (figure 7) to to
knock out the shaft pins, (key 10) through the shaft
and ball lugs.

Note

The punch dimensions should be as
per table 6 to avoid damaging the ball

Содержание V150S

Страница 1: ... avoid personal injury or property damage it is important to carefully read understand and follow all the contents of this manual including all safety cautions and warnings If you have any Figure 1 Fisher V150S Slurry Vee Ball Control Valve W8511 questions about these instructions contact your Emerson Process Management sales office before proceeding Description The V150S Slurry Vee Ball valve sho...

Страница 2: ...s Part Material Valve Body Carbon Steel ASTM A216 WCC Body Liner High Chrome Iron ASTM A532 Class III Type A V notch Ball High Chrome Iron ASTM A532 Class III Type A Flow Ring High Chrome Iron ASTM A532 Class III Type A Flow Ring Insert type optional High Chrome Iron ASTM A532 Class III Type A Flow Ring Retainer Carbon Steel ASTM A105 Bearing Shroud High Chrome Iron ASTM A532 Class III Type A Bear...

Страница 3: ...to protect against process media If installing into an existing application also refer to the WARNING at the beginning of the Maintenance section in this instruction manual Figure 3 Optional Shaft to Body Bonding Strap Assembly VALVE BODY ACTUATOR A A VIEW A A 24 E0880 CAUTION When ordered the valve configuration and construction materials were selected to meet particular pressure temperature pres...

Страница 4: ...8 18 11 81 11 97 10 63 5 19 1 50 9 25 1 81 0 69 1 Stud length associated with clearance dimension M is longer than standard length specified in ANSI B16 5 2 Clearance necessary to remove flange bolts B M N A G K D S DIAMETER U W T NPS 3 THROUGH 12 E0875 Figure 4 Fisher V150S Dimensions see table 4 Table 5 Fisher V150S Dimensions for Double D Shaft Drive VALVE SIZE E S 1 FLAT LENGTH T U W DN mm 80 ...

Страница 5: ...e taken to protect against process media Packing Maintenance 1 It is recommended that the valve be removed from the line when replacing packing to allow correct set up of the actuator after actuator removal 2 Remove the packing follower nuts and packing follower keys 18 and 16 3 Remove the packing parts see figure 4 and keys 15 and 14 using a purposed designed packing extraction tool to avoid dama...

Страница 6: ...NING at the beginning of the Maintenance section Reference figures 9 and 10 CAUTION Trim parts are made from brittle material handle with care to avoid chipping or breakage 1 Clean all surfaces of the parts to be used Ensure all mating surfaces are in good condition and free from scratches and dents Replace worn parts Fit new gaskets key 13 and 21 and packing key 15 2 Position the valve body with ...

Страница 7: ...ecommendations for assembly can be provided by your Emerson Process Management sales office Actuator Mounting Use the appropriate actuator instruction manual this section of this manual and figure 8 of this manual when mounting the actuator or changing actuator styles and positions 1 To help ensure correct centering of the V notch ball key 3 on the flow ring key 4 or 28 29 be sure the ball is clos...

Страница 8: ...l injury keep hands tools and other objects away from the ball while stroking the valve 2 Rotate the ball to the closed position 3 Position the ball in the proper location 4 The ball is in its closed position when the Vee plane of the ball opposite the convex side is parallel to the liner end flange face of the valve body Measure to check Adjust the actuator linkage or travel stops to position CAU...

Страница 9: ...pecify the complete 11 character part number from the parts kits or parts list information WARNING Use only genuine Fisher replacement parts Components that are not supplied by Emerson Process Management should not under any circumstances be used in any Fisher valve because they may void your warranty might adversely affect the performance of the valve and could cause personal injury and property ...

Страница 10: ...V150S Slurry Vee Ball Valve Instruction Manual November 2010 10 Figure 10 Fisher V150S Assembly E0879 ...

Страница 11: ...12183U012 NPS 10 2B12185U012 NPS 12 3B12213U012 Schedule 80 NPS 3 1B12085U012 NPS 4 1B12111U012 NPS 6 2B12019U012 NPS 8 2B12184U012 NPS 10 2B12186U012 NPS 12 3B12215U012 Key Description Part Number 5 Flow Ring Retainer 6 Bearing Shroud High Chrome Iron 2 req d NPS 3 1B12100U012 NPS 4 1B12100U012 NPS 6 1B12062U012 NPS 8 1B12170U012 NPS 10 1B12170U012 NPS 12 1B12201U012 7 Bearing 440C 2 req d NPS 3 ...

Страница 12: ...mirates Singapore 128461 Singapore www Fisher com The contents of this publication are presented for informational purposes only and while every effort has been made to ensure their accuracy they are not to be construed as warranties or guarantees express or implied regarding the products or services described herein or their use or applicability All sales are governed by our terms and conditions ...

Отзывы: