Construction Guide
Ridge Assembly
Your PPP has a central ridge that suspends
underneath each of your hoops.
On 10ft and 15ft PPP the ridge tube comes in
sections, you will need to assembly these sections
together as in
(dia 6a & 6b)
. When assembling the
ridge tube to the hoops make sure that the screw
heads are on the inside, so they don’t damage the
covering.
This ridge is fixed onto the hoop using the ridge
clamps (R2525).
Tighten the end clamps with the
end of the ridge tube protruding as little as possible
through the clamp. On the end hoops, make sure the
threaded section of the clamp is to the inside of the
PPP
(dia 11)
. Use the silver protection tape (SPT1) to
wrap around the ridge clamps and ridge tube ends
to prevent any damage to the cover
(dia 11 detail)
.
Ventilation Legs
Ventilation legs (25/50FS) fix onto the bolts of the
corner brackets that’s used to fix the timber side rail.
Fix the leg onto the bolt using the supplied Nyloc
nut (M8NYLOC)
(dia 12)
. This allows the leg to swivel
into a position that holds the PPP off the ground for
ventilation
(dia 12 detail)
, alternatively they can be
folded away when not in use.
Covering
Whichever cover you choose, the method of fixing is
the same. Lay the cover over the frame and centralise
in each direction
(dia 13)
.
Starting at one end of the PPP, use a staple gun
to staple the cover in the centre of one of the end
timbers
(dia 14)
.
At the opposite end pull the cover tight along the
length and once again staple the cover to the centre
of the end timber rail.