Page 17
CYGHPG-User-Manual-v2
2.4.4 Connect The AC Output
2.4.4.1 Connecting with CEE Form Industrial Plugs
1.
Before any power connections are made, ensure that Cygnus HPG is
in Mode 4: Off. See
"3.1.1 Description Of The Power Modes" on page
18
2.
Ensure that the output breakers are switched down into the off
position. S
ee
"Fig. 5 - Inputs, Outputs and Circuit Breakers" on page
16
3.
Ensure that the CEE Form connectors to be used are dry; wipe off any
excess moisture with an absorbent cloth.
4.
Plug the electrical consumers in to a 230 V AC Out CEE Form socket:
blue for single phase or red for three phase. See
"Fig. 5 - Inputs,
Outputs and Circuit Breakers" on page 16
2.4.4.2 Connecting by Hard Wiring Into The Bus Bar
1.
Before any power connections are made, ensure that Cygnus HPG is
in Mode 4: Off. See
"3.1.1 Description Of The Power Modes" on page
18
2.
Open the main door by unlocking the three locks located at its right
hand side using the provided 5 mm double barb key See
"Fig. 6 - 5 mm
Double Barb Key" on page 17
.
3.
The Bus Bar is located at the bottom left corner.
4.
Pass the cables through the rubber flap in the door and connect to the
lower row of connections using 10 mm ring terminals.
5.
Remove the 17 mm nuts.
6.
Attach ring terminals, referring to
"Fig. 7 - AC Output Bus Bar
Connections" on page 17
7.
Replace and tighten the 17 mm nuts.
Fig. 6 -
5 mm Double Barb Key
Fig. 7 -
AC Output Bus Bar
Connections
L1 L2 L3 N
E