Doc# 71-0170
4215-141
Rev. 02
10
08/23/2022
43.
Confirm everything is working. After confirmation, do the final
installation of the control and see Himalaya installation manual for
complete heater instructions.
NOTE: At this point, prior to the completion of the room assembly,
apply power to the heater and control panel to verify that the
proper wiring connections have been made throughout the sauna
assembly process.
Corner Cap / Final Corner Panel Installation / Finishing Trim
44.
Place the remaining back corner panel into position using the base
groove as a guide and make flush the entire length of the corner
panels before securing them together using the pre-drilled holes
and 3” screws provided. Route the control panel cable through the
hole in the remaining top plate.
(Image 22)
45.
Locate exterior corner trim pieces and match the numbered corner
trim piece to the corresponding numbered sauna frame corners.
Position each corner trim piece into place and attach with 1-
1/2”
brad nails or finish nails.
(Image 23)
46.
Locate top trim (fascia trim) pieces. Start with the side and cut the
two side pieces to length and attach with brad or finish nails.
47.
Cut the front top trim (fascia trim) piece so that it covers the front
ends of both side trim pieces and attach with brad or finish nails.
(Image 24)
48.
Cut to length the interior ceiling trim (cover molding) pieces,
starting with the back wall and then the two side walls and secure
them into place with brand or finish nails. Screw head buttons are
included for backrest. A light hammer tap may be needed, and
glue can help secure the buttons.
Note
: Cove Molding (5/16” x 1”) will be provided longer than
needed to allow trimming to exact size to insure a tight fit.
49.
Vent Valve and Vent Grill are pre-Installed.
Note: front
facia will
overlap side
facia when
using butt
joint.
Image 22
Image 23
Image 24